Phase 5 of 6 · GC project lifecycle
Execution: the operating rhythm that runs a commercial job
Execution is not a sequence of steps. It is a loop. The same routines run every day, week and month until the building is substantially complete, and the health of the job is the health of those routines.
The swimlane below follows one loop from the field to the money: the day's work and documents, the weekly coordination, then the monthly cycle of cost, forecast, billing and executive review. The operating rhythm page shows the same routines on a calendar.
By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC
- Purpose
- Build safely to schedule and quality while keeping documents, changes, cost and billing current, so the forecast and the cash position are true every month.
- Roles involved
- Executive Leadership, Project Manager, APM / Project Engineer, Superintendent, Purchasing, Accounting / Finance
- Starts with
- Mobilization: Notice to proceed, PEP, live systems, billing calendar
- Gate
- Substantial completion
The workflow, animated
Press play to follow the work across roles, or step through it. Select any step for who does it, inputs, outputs, the decision rule, typical systems, common failure points, and what to automate and measure.
1 / 13: Huddle and daily log
Step 1 of 13 · Superintendent
Huddle and daily log
Start the day with foremen, end it with a daily log: manpower, weather, work done, deliveries, delays and photos.
- Who
- Superintendent
- Inputs
- Look-ahead; Sign-in sheets; Photos
- Outputs
- Daily log; Delay notices
- Done when
- A complete log exists for every workday.
- Common failure points
- Logs written days later from memory, useless in a dispute
- What to automate
- Draft the daily log from sign-ins, weather data and photos for the superintendent to confirm.
- What to measure
- Workdays without a completed log
Tap a step for its details.
Amber boxes are decisions. Dashed shapes are handoffs to another phase. Dashed lines loop back. Roles and steps are typical; adapt them to your company.
Step by step
The 13 steps of execution operating rhythm, in order.
- 1Superintendent
Huddle and daily log
Start the day with foremen, end it with a daily log: manpower, weather, work done, deliveries, delays and photos.
- Inputs
- Look-ahead; Sign-in sheets; Photos
- Outputs
- Daily log; Delay notices
- Done when
- A complete log exists for every workday.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Logs written days later from memory, useless in a dispute
- Automate and measure
- Draft the daily log from sign-ins, weather data and photos for the superintendent to confirm. Measure: workdays without a completed log.
Next: Three-week look-ahead · RFIs and submittals
- 2Superintendent
Three-week look-ahead
Each week, trades commit to the next three weeks of work and name their constraints.
- Inputs
- Schedule; Last week's commitments
- Outputs
- Look-ahead; Constraint log
- Done when
- Only tasks with constraints cleared are committed.
- Typical systems
- Scheduling (e.g., Primavera P6, Outbuild, Microsoft Project)
- Watch for
- A look-ahead that is a copy of the master schedule, not a trade commitment
- Automate and measure
- Feed look-ahead progress back into the master schedule update. Measure: committed tasks completed as planned.
Next: Quality and safety inspections
- 3APM / Project Engineer
RFIs and submittals
Write, route and chase RFIs and submittals; distribute answers and approved submittals to the field.
- Inputs
- Field questions; Submittal register
- Outputs
- Answered RFIs; Approved submittals; Potential change flags
- Done when
- Every RFI that may cost money or time is flagged as a potential change on the day it is answered.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- An RFI answer that changes scope never reaches the change log
- Automate and measure
- Flag RFI answers with cost or schedule impact and open a change event automatically. Measure: average days open; overdue ball-in-court items.
Next: Change management
- 4Superintendent
Quality and safety inspections
Run inspections and observations, correct issues, and track deficiencies to closure.
- Inputs
- Inspection checklists; Safety plan
- Outputs
- Inspection records; Deficiencies assigned to trades
- Done when
- Deficiencies are assigned with a due date the day they are found.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Deficiencies pile up and become the punch list
- Automate and measure
- Remind trades of open deficiencies and escalate aged items. Measure: deficiencies open longer than 14 days.
Next: Weekly OAC meeting
- 5Project Manager
Change management
Turn each change event into a priced proposal, an owner change order and matching sub change commitments.
- Inputs
- Change events; Sub pricing; Owner direction
- Outputs
- Pending change orders; Executed owner change orders
- Done when
- No extra work proceeds without written direction, and every approved owner change has its sub side committed.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
- Watch for
- Approved work billed late or never because the change order sat unsigned
- Automate and measure
- Age every change by status and alert when approved changes are not yet billed or committed. Measure: pending change value and average age.
Next: Weekly OAC meeting · Sub change commitments
- 6Project Manager
Weekly OAC meeting
Owner, architect and contractor review progress, decisions needed, RFIs, submittals and changes.
- Inputs
- Open items; Schedule status; Change log
- Outputs
- Minutes with decisions and owners
- Done when
- Minutes go out within 48 hours, with owners and dates on every action.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- The same items carried for weeks with no decision
- Automate and measure
- Build the agenda from open RFIs, submittals and changes in the PM system. Measure: owner decisions past due.
Next: Monthly cost-to-complete
- 7Purchasing
Sub change commitments
Issue change orders to subs and POs for new material, tied to the owner change where one exists.
- Inputs
- Approved change; Sub pricing
- Outputs
- Commitment change orders by cost code
- Done when
- Commitment changes are entered once and appear in both the PM system and the ERP.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
- Watch for
- Sub change orders paid that were never recovered from the owner
- Automate and measure
- Link sub change commitments to owner change orders and report the unrecovered gap. Measure: sub changes with no matching owner change.
Next: Cost cutoff and AP coding
- 8Project Manager
Monthly cost-to-complete
Re-forecast each cost code: cost to date, open commitments, pending changes, and what is left to spend.
- Inputs
- Job cost report; Commitments; Pending changes; Field progress
- Outputs
- Projected final cost; Fade or gain explanation
- Done when
- Every code with a material change from last month has a written reason.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum); Spreadsheets (e.g., Excel)
- Watch for
- Forecast equals budget until the last month, when the fade arrives all at once
- Automate and measure
- Pre-fill the forecast from cost, commitments and pending changes so the PM edits judgment, not arithmetic. Measure: projected margin change month over month.
Next: Pay application
- 9Accounting / Finance
Cost cutoff and AP coding
Code every invoice, card charge and timecard to the right job and cost code before the cutoff.
- Inputs
- Invoices; Card transactions; Payroll
- Outputs
- Posted job cost; Uncoded items list
- Done when
- Nothing material is left uncoded at cutoff.
- Typical systems
- Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum); Spend management (e.g., Ramp); Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Card spend sits in a suspense account for weeks Costs show in the ERP but not the PM system
- Automate and measure
- Code card and invoice lines from receipts and POs, sync posted cost to the PM system, and chase the uncoded list. Measure: uncoded spend at cutoff.
Next: Monthly cost-to-complete
- 10Project Manager
Pay application
Agree a pencil draft, then submit the pay app with sub pay requests, change orders and lien waivers.
- Inputs
- SOV; Sub pay requests; Executed change orders; Lien waivers
- Outputs
- Pay application submitted
- Done when
- Submitted by the contract due date, with every billed change executed.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
- Watch for
- Pay app built in a spreadsheet and re-keyed into accounting
- Automate and measure
- Generate the pay app from the SOV and send it to accounting as an invoice without re-keying. Measure: days from period end to submission.
Next: Billing, AR and sub payments
- 11Accounting / Finance
Billing, AR and sub payments
Invoice the owner, collect, pay subs against approved requests and waivers, and track retainage both ways.
- Inputs
- Approved pay app; Sub invoices; Lien waivers
- Outputs
- AR and AP updated; Retainage receivable and payable
- Done when
- Subs are paid only with current waivers and compliance.
- Typical systems
- Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
- Watch for
- Sub paid without a waiver, or before the owner paid on pay-when-paid terms
- Automate and measure
- Hold sub payments automatically until waivers and compliance documents are current. Measure: days sales outstanding; retainage held.
Next: Monthly project review
- 12Executive Leadership
Monthly project review
Leadership reviews forecast margin, over/under billing, cash and risk for every job on the WIP schedule.
- Inputs
- Forecasts; Billings; AR aging
- Outputs
- WIP schedule; Actions on troubled jobs
- Done when
- Every job with fade or underbilling has an owner and a plan.
- Typical systems
- Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum); Reporting (e.g., Power BI, Microsoft Fabric); Spreadsheets (e.g., Excel)
- Watch for
- WIP stitched together in spreadsheets from three systems every month
- Automate and measure
- Build WIP from the ERP and the PM system on a schedule, with exceptions highlighted. Measure: portfolio margin fade; over/under billing.
Next: Substantially complete?
- 13Superintendent
Decision: Substantially complete?
When the building can be used for its purpose, the job moves to handover. Until then, the loop repeats.
- Inputs
- Progress; Inspections
- Outputs
- Handover starts, or another cycle
- Decision rule
- Yes when the owner can occupy and use the work, subject to punch list.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Scheduling (e.g., Primavera P6, Outbuild, Microsoft Project)
- Watch for
- Declaring completion before inspections are passed
- Automate and measure
- Track the completion checklist against inspections and punch status. Measure: forecast versus contract completion date.
Next: No → Huddle and daily log
Roles in this phase
- Executive Leadership
- Reviews WIP monthly and steps in on troubled jobs.
- Project Manager
- Owns changes, OAC, forecast and the pay application.
- APM / Project Engineer
- Runs RFIs and submittals and keeps the logs current.
- Superintendent
- Runs the site: daily log, look-ahead, inspections and quality.
- Purchasing
- Issues sub change orders and material POs.
- Accounting / Finance
- Cost cutoff, AP coding, billing, AR, sub payments and WIP.
See the full typical RACI across every phase.
Handoffs in and out
Comes in
- From Mobilization: Notice to proceed, PEP, live systems, billing calendar
Goes out
- To Handover and closeout: Substantial completion, punch list, change log, forecast and billing status
- To Finance (continuous): Monthly pay apps, coded cost, forecasts for WIP
Gate checklist
Substantial completion
Can the owner use the building for its intended purpose?
- Punch list issued, assigned to trades, and tracked to closure
- Final inspections passed; certificate of occupancy (temporary or final) issued
- Life-safety and building systems commissioned and tested
- Owner training sessions held and recorded
- Substantial completion certificate signed by owner and architect
- Warranty start date agreed and written down
Owner: Project Manager. Sign-off: PM, Super, Exec.
Common pitfalls
RFIs that never become changes
An answer that adds scope must open a change event the same day, or the money is gone.
Unsigned approved changes
Work done on verbal approval cannot be billed. Age every change by status.
Double entry between PM and accounting
Commitments, changes and pay apps keyed twice drift apart. The difference appears at WIP.
Forecast equals budget
A forecast that never moves is not a forecast. Fade shows up all at once at the end.
Month-end stitching
If WIP is built by hand from three systems, it is late, and nobody trusts it.
KPIs to watch
- Projected margin vs bid
- Forecast margin compared with the margin at award, month over month.
- Over/under billing
- Billings to date minus earned revenue (percent complete times contract value).
- Pending change exposure
- Value and age of changes not yet executed with the owner.
- RFI cycle time
- Average days from RFI creation to answer, and items past due.
- Look-ahead reliability
- Share of committed weekly tasks completed as planned.
Definitions for WIP, over/under billing, AR and cash are in the metric dictionary. For the recurring meetings where these get reviewed, see the operating rhythm.
What to automate between systems
Most of the rework in this phase happens where one system hands data to another. Start with the handoff your team re-keys most often.
Commitment and change sync
Enter subcontracts, POs and change orders once and sync them between the PM system and the ERP, so committed cost agrees without re-keying.
Cost coding at the source
Code card spend and invoices to job and cost code when they arrive, and push posted cost back to the PM system for the forecast.
Pay app to invoice
Generate the owner invoice in accounting from the approved pay app instead of typing it in.
WIP without the spreadsheet
Assemble WIP, over/under billing and the project scorecard from both systems on a schedule, and spend the meeting on exceptions.
Frequently asked questions
What is the operating rhythm of a construction project?
The recurring routines that run a job: daily huddles, logs and inspections; weekly trade coordination, OAC and internal meetings; and the monthly cycle of cost cutoff, forecast, pay application, owner report and WIP review.
How do change orders flow on a GC project?
A field issue or RFI answer becomes a change event, which is priced with subs into a pending change order, submitted to the owner, executed, billed, and matched with sub change commitments. Each status should be aged and reported.
What is cost-to-complete?
The PM's estimate of the remaining cost on each cost code. Cost to date plus cost to complete gives the projected final cost, which drives forecast margin and percent complete for WIP.
Why do PM and accounting numbers disagree?
Usually because commitments, changes or costs were entered separately in each system, coded differently, or captured at different cutoff dates. An integration or a shared cost code structure removes most of it.
Related on Build Flows