GC project lifecycle · typical roles

GC project roles and responsibilities (typical RACI)

Who does what on a commercial job, from the first estimate to the closed file. This is a typical RACI for a mid-sized general contractor, not a standard. Titles and splits vary: in smaller firms the PM also runs purchasing, and in larger ones project controls and risk are separate teams.

Use it as a starting point. Mark where your company differs, then agree it with the people in each role.

By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC

The roles

Eight roles appear across the lifecycle. Each phase page shows them as swimlanes.

Executive Leadership
Principals and operations executives. They decide what to pursue, approve price and risk, sign contracts, and review the health of every job in the portfolio.
Estimating / Preconstruction
Builds the price: scope review, takeoff, sub coverage, bid leveling, and the assumptions behind the number. On negotiated work they also lead design-phase budgeting and value engineering.
Project Manager
Owns the job commercially: contract, budget, schedule of values, change orders, forecast, owner relationship, and the monthly pay application.
APM / Project Engineer
Runs the document flow: RFIs, submittals, drawing sets, meeting minutes, procurement logs, and closeout documents.
Superintendent
Runs the site: logistics, trade sequencing, the three-week look-ahead, daily logs, safety and quality in the field, and punch list.
Operations Support
Safety, risk and insurance, compliance, permitting, and project administration. Often a shared team that supports several jobs at once.
Accounting / Finance
Job setup in the ERP, AP and cost coding, billing and AR, sub payments and lien waivers, retainage, WIP, and month-end close.
Purchasing
Buyout: subcontracts, purchase orders, material procurement, and change commitments to subs. In smaller GCs this work sits with the PM or estimating.

Typical RACI by phase

Labeled typical: adapt it before you adopt it.

  • RResponsible: does the work
  • AAccountable: owns the outcome and signs off (one per row)
  • CConsulted: gives input before the work is done
  • IInformed: told after the decision or result

Estimating and award

  • Go / no-go to pursue

    • AExec
    • REstimating
    • CPM
    • COps support
  • Takeoff, sub coverage and bid leveling

    • AEstimating
    • CPM
    • CSuper
    • CPurchasing
  • Final price and bid approval

    • AExec
    • REstimating
    • CPM
    • IAccounting

Contract alignment

  • Prime contract review and negotiation

    • AExec
    • RPM
    • CEstimating
    • COps support
    • CAccounting
  • Estimate to budget, cost code mapping

    • APM
    • REstimating
    • CAccounting
  • Job setup in the accounting system

    • AAccounting
    • CPM
  • Schedule of values

    • APM
    • CEstimating
    • CAccounting

Preconstruction and procurement

  • Baseline schedule

    • APM
    • RSuper
    • CAPM / PE
    • IExec
  • Buyout and subcontract award

    • APM
    • RPurchasing
    • CExec
    • CEstimating
    • IAccounting
  • Subcontractor compliance (COI, W-9, licenses)

    • AOps support
    • RPurchasing
    • CAccounting
    • IPM
  • Permits and approvals

    • APM
    • ROps support
    • CSuper

Mobilization

  • Project execution plan

    • APM
    • RAPM / PE
    • RSuper
    • COps support
    • IExec
  • Site logistics and safety plan

    • ASuper
    • ROps support
    • CPM
  • Billing and cost coding setup

    • AAccounting
    • RPM
    • IAPM / PE

Execution

  • Daily log and look-ahead

    • ASuper
    • CAPM / PE
    • IPM
  • RFIs and submittals

    • APM
    • RAPM / PE
    • CSuper
  • Change orders (owner and sub)

    • APM
    • RAPM / PE
    • RPurchasing
    • CExec
    • IAccounting
  • Monthly cost-to-complete forecast

    • APM
    • CSuper
    • CAccounting
    • IExec
  • Pay application and lien waivers

    • APM
    • RAccounting
    • CAPM / PE
  • WIP and over/under billing

    • AAccounting
    • CPM
    • IExec

Handover and closeout

  • Punch list and commissioning

    • ASuper
    • RAPM / PE
    • CPM
  • Closeout documents and owner training

    • APM
    • RAPM / PE
    • CSuper
  • Final billing, retainage and job close

    • AAccounting
    • RPM
    • IExec
  • Lessons learned

    • AExec
    • RPM
    • CEstimating
    • CSuper

Making a RACI stick

  • Exactly one A per activity. Two accountable people means nobody is.
  • Tie each A to a gate or a recurring routine, so accountability shows up on a calendar, not just a chart.
  • Give each role a view in the systems that matches its row: the PM sees the change log, accounting sees uncoded spend, leadership sees the scorecard.
  • Revisit it after the first project that uses it. The gaps will be obvious by then.

Frequently asked questions

What is a RACI matrix in construction?

A table that lists project activities against roles and marks who is Responsible (does the work), Accountable (owns the outcome, one per activity), Consulted (gives input first) and Informed (told afterwards). It removes the most common source of dropped work: two people each assuming the other has it.

What is the difference between a project manager and a superintendent?

The project manager owns the job commercially: contract, budget, changes, forecast, billing and the owner relationship. The superintendent owns the site: logistics, sequencing, trade coordination, daily logs, safety and quality in the field. They share the schedule.

What does an assistant project manager or project engineer do?

They run the document flow: RFIs, submittals, drawing sets, meeting minutes, procurement and submittal logs, and the closeout package. It is usually the training ground for future project managers.

Who should be accountable for cost codes and job setup?

Accounting is typically accountable for the job and cost code structure in the ERP, with the PM consulted. What matters most is that one structure is used in the project management system, the ERP and the spend management tool.