How a commercial GC runs a project, end to end
A commercial general contractor runs every job through the same six phases: win it, sign it, plan and buy it, mobilize, build it under a steady operating rhythm, and close it out. Purchasing and finance run underneath the whole way.
This guide walks through each phase as an animated workflow: who does what, what passes between people, the decision at each gate, and where the work usually breaks. It describes typical practice at a mid-sized commercial GC. Adapt the roles and steps to your company.
By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC
The lifecycle at a glance
Tap a phase to open its workflow. The diamonds are gates: short checklists that must be true before the job moves on.
Phase 1
Estimating and award
From a new opportunity to a signed award: decide to pursue, build a complete price, and approve the risk.
Gate: a short checklist that must be true before the job moves on.
Gate: Go / no-go to pursue
Estimating and awardFrom a new opportunity to a signed award: decide to pursue, build a complete price, and approve the risk.Open the workflowGate: Bid approval
- Contract alignmentSign a contract you understand, then make the budget, the schedule of values and the accounting setup agree.Open the workflow
Gate: Contract executed, budget locked
- Preconstruction and procurementBuy out the job, build the baseline schedule, get the permits moving, and start long-lead items early.Open the workflow
Gate: Ready to mobilize
- MobilizationPut the plan, the people, the site and the systems in place so the first month of work runs on rails.Open the workflow
Gate: Ready for construction (NTP)
- Execution operating rhythmDaily field routines, weekly coordination, and a monthly commercial cycle, repeated until substantial completion.Open the workflow
Gate: Substantial completion
- Handover and closeoutFinish the punch list, hand the owner a working building and its documents, then close every dollar.Open the workflow
Gate: Financial closeout
Purchasing runs underneath
Carry numbers, buyout, subcontracts and POs, change commitments, sub closeout.
Finance runs underneath
Job setup, billing calendar, cost cutoff and pay apps, WIP every month, retainage and close.
Who this is for
- New project managers, APMs and project engineers learning how a commercial job runs from start to finish.
- Operations leaders writing down how their company works, or onboarding people from other firms.
- Accounting and finance teams who want to see where project data comes from before it reaches the books.
- Anyone planning software or integrations, who needs to know which handoffs matter.
How to use it
- Start here for the shape of the whole job, then open one phase.
- Press play on the swimlane, or step through it. Tap any step for who, inputs, outputs, the decision rule and what to measure.
- Use the gate checklists in your own kickoff and review meetings. They print cleanly.
- Compare the typical roles with your own org chart, and mark where your company differs.
The six phases
Each phase has an owner, a gate at the end, and a handoff to the next. Most problems on a job can be traced to one handoff that was rushed.
- Phase 1Estimating and awardFrom a new opportunity to a signed award: decide to pursue, build a complete price, and approve the risk.Gate: Go / no-go to pursue; Bid approvalRoles: Exec, Estimating, PM, Super, Ops support14 steps
- Phase 2Contract alignmentSign a contract you understand, then make the budget, the schedule of values and the accounting setup agree.Gate: Contract executed, budget lockedRoles: Exec, Estimating, PM, Ops support, Accounting12 steps
- Phase 3Preconstruction and procurementBuy out the job, build the baseline schedule, get the permits moving, and start long-lead items early.Gate: Ready to mobilizeRoles: Estimating, PM, APM / PE, Super, Purchasing, Ops support13 steps
- Phase 4MobilizationPut the plan, the people, the site and the systems in place so the first month of work runs on rails.Gate: Ready for construction (NTP)Roles: Exec, PM, APM / PE, Super, Ops support, Accounting11 steps
- Phase 5Execution operating rhythmDaily field routines, weekly coordination, and a monthly commercial cycle, repeated until substantial completion.Gate: Substantial completionRoles: Exec, PM, APM / PE, Super, Purchasing, Accounting13 steps
- Phase 6Handover and closeoutFinish the punch list, hand the owner a working building and its documents, then close every dollar.Gate: Substantial completion; Financial closeoutRoles: Exec, PM, APM / PE, Super, Ops support, Accounting12 steps
Key gates
Seven decisions move a job from pursuit to a closed file. Each has an owner and a short checklist.
- G1Go / no-go to pursueIs this a job we should spend estimating hours on?Owner: Executive Leadership
- G2Bid approvalIs the price complete, covered, and worth the risk?Owner: Executive Leadership
- G3Contract executed, budget lockedDo the contract, the budget and the books agree?Owner: Project Manager
- G4Ready to mobilizeCan we put people on site without stopping in week two?Owner: Project Manager
- G5Ready for construction (NTP)Is every system, plan and person in place for day one?Owner: Executive Leadership
- G6Substantial completionCan the owner use the building for its intended purpose?Owner: Project Manager
- G7Financial closeoutIs every dollar billed, paid, released and explained?Owner: Accounting / Finance
The handoffs
What passes from one phase to the next. If the receiving team gets a summary instead of the full package, they rebuild it from scratch.
| From | To | What changes hands |
|---|---|---|
| Estimating and award | Contract alignment | Award notice, final estimate, proposal, exclusions, leveling sheets and assumptions |
| Estimating and award | Purchasing (continuous) | Carry numbers and the subs who priced each package |
| Contract alignment | Preconstruction and procurement | Executed contract, locked budget, approved SOV, turnover notes and risk register |
| Contract alignment | Finance (continuous) | Job setup, billing terms, retainage rate and SOV for pay applications |
| Preconstruction and procurement | Mobilization | Baseline schedule, executed subcontracts, permits status, logistics plan, submittal register |
| Preconstruction and procurement | Purchasing (continuous) | Buyout log with remaining packages and award-by dates |
| Mobilization | Execution | Notice to proceed, PEP, live document control, billing calendar, a running site |
| Mobilization | Finance (continuous) | Billing calendar, lien waiver rules and cost coding rules |
| Execution operating rhythm | Handover and closeout | Substantial completion, punch list, change log, forecast and billing status |
| Execution operating rhythm | Finance (continuous) | Monthly pay apps, coded cost, forecasts for WIP |
| Handover and closeout | Estimating (next bid) | Final unit costs, margin versus bid, and lessons learned |
| Handover and closeout | Warranty | Warranty log, start dates and trade contacts |
Purchasing and finance run underneath
Two streams do not belong to any one phase.
Purchasing
Starts with the carry numbers in the estimate, becomes the buyout plan in preconstruction, issues subcontracts and purchase orders, handles change commitments during construction, and closes every subcontract at the end. The measure that matters is buyout variance: budget minus committed cost, package by package.
Finance
Sets up the job and cost codes after award, agrees the billing calendar at mobilization, then runs the monthly cycle of cost cutoff, pay application, AR, sub payments and WIP until retainage is collected and the job is closed. The measures that matter are over/under billing, projected margin and cash.
Where the systems double-enter
A typical commercial GC runs project management (e.g., Procore), accounting / ERP (e.g., Sage, Viewpoint Vista), scheduling (e.g., Primavera P6, Outbuild) and spend management (e.g., Ramp). The lifecycle crosses between them at three points.
Browse the systems by category in the construction systems atlas: project management, accounting / erp, scheduling, spend management.
Also in this guide
Frequently asked questions
What are the phases of a commercial construction project for a general contractor?
Most commercial GCs move a job through six phases: estimating and award, contract alignment, preconstruction and procurement, mobilization, execution under a daily, weekly and monthly operating rhythm, and handover and closeout. Purchasing (buyout and change commitments) and finance (billing, cost and cash) run continuously underneath all six.
Who owns a project at each phase?
Estimating owns the job until award. The project manager takes commercial ownership at contract alignment and keeps it through closeout, with the superintendent owning the site from mobilization onward. Accounting owns job setup, billing records and the final financial close. Leadership approves the gates.
What is a stage gate in construction project delivery?
A gate is a short checklist that must be true before the job moves to the next phase, such as a signed contract and a budget that ties to the books before procurement starts. Gates exist because the cost of a missing item grows the further the job moves without it.
Is this guide specific to one software platform?
No. Systems are named by category with common examples: project management (e.g., Procore), accounting and ERP (e.g., Sage, Viewpoint Vista), scheduling (e.g., Primavera P6, Outbuild), and spend management (e.g., Ramp). The workflow is the same whichever tools you run.
Can I use these workflows to train new project managers and engineers?
Yes. That is what they are for. Each phase page has a step-by-step swimlane, the roles involved, the gate checklist and common failure points. Adapt the roles and steps to your own company before you treat them as policy.
Where does double entry usually happen across the lifecycle?
At three handoffs: when the estimate becomes a budget in both the project management system and the ERP, when commitments and change orders are created in one system and re-keyed into the other, and at month end when cost, billing and forecast are stitched together in spreadsheets for WIP.
Related on Build Flows
Next step
Want your lifecycle to run on connected systems?
Tell us which handoffs your team re-keys today: estimate to budget, commitments, change orders, cost coding or month-end WIP. We'll show you what connecting them would look like.
Prefer email? charley@buildflows.ai