Phase 4 of 6 · GC project lifecycle
Mobilization: getting a commercial job ready for day one
Mobilization is short, but it decides how the first months go. The site gets set up, the team agrees how the job will be run, and the systems that will carry RFIs, submittals, costs and billing are configured before the first invoice arrives.
Most data problems that show up at month end were set up here: cost coding rules nobody published, a billing format the owner never agreed, or a folder structure every engineer invented for themselves.
By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC
- Purpose
- Start construction with a written execution plan, a safe and organized site, working document control, and billing and cost rules everyone follows from the first invoice.
- Roles involved
- Executive Leadership, Project Manager, APM / Project Engineer, Superintendent, Operations Support, Accounting / Finance
- Starts with
- Preconstruction and procurement: Baseline schedule, subcontracts, permits, logistics plan, submittal register
- Gate
- Ready for construction (NTP)
The workflow, animated
Press play to follow the work across roles, or step through it. Select any step for who does it, inputs, outputs, the decision rule, typical systems, common failure points, and what to automate and measure.
1 / 11: Project alignment review
Handoff 1 of 11 · Project Manager
Project alignment review
The full team reviews the contract, budget, schedule, buyout status and risks before mobilizing.
- Who
- Project Manager
- Inputs
- Precon outputs; Risk register
- Outputs
- Agreed priorities; Open item list
- Done when
- Done when the team agrees on the top risks and who owns each one.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Common failure points
- Each person mobilizes from their own assumptions
- What to automate
- Prefill the review deck from the budget, schedule and buyout log.
- What to measure
- Open items at the review
Tap a step for its details.
Amber boxes are decisions. Dashed shapes are handoffs to another phase. Dashed lines loop back. Roles and steps are typical; adapt them to your company.
Step by step
The 11 steps of mobilization, in order.
- 1Project Manager
Handoff: Project alignment review
The full team reviews the contract, budget, schedule, buyout status and risks before mobilizing.
- Inputs
- Precon outputs; Risk register
- Outputs
- Agreed priorities; Open item list
- Done when
- Done when the team agrees on the top risks and who owns each one.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Each person mobilizes from their own assumptions
- Automate and measure
- Prefill the review deck from the budget, schedule and buyout log. Measure: open items at the review.
Next: Project execution plan · Site setup · Site-specific safety plan
- 2Project Manager
Project execution plan
Write how this job will be run: team, responsibilities, communication, meeting cadence, procedures and reporting.
- Inputs
- Company standards; Contract requirements
- Outputs
- Project execution plan (PEP)
- Done when
- The PEP names an owner for every recurring routine and report.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- A PEP written for the file and never used
- Automate and measure
- Generate the PEP from a template with the contract's key requirements pulled in. Measure: pEP routines actually running after 60 days.
Next: Document control setup · Billing and cost setup
- 3Superintendent
Site setup
Install trailers, temporary power and water, site protection, signage, sanitation and hoisting per the logistics plan.
- Inputs
- Logistics plan; Permits
- Outputs
- Site ready for trades
- Done when
- Done when the site is safe and accessible for the first trades.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Temporary utilities ordered late
- Automate and measure
- Track temporary facility orders with dates against the mobilization schedule. Measure: days from NTP to first trade on site.
Next: Pre-mobilization meetings with trades
- 4Operations Support
Site-specific safety plan
Write the safety plan for this site's hazards, emergency procedures and orientation.
- Inputs
- Company safety program; Logistics plan; Scope of work
- Outputs
- Approved safety plan; Orientation schedule
- Done when
- No one works on site without orientation.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive); Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- A generic plan that does not mention this site's real hazards
- Automate and measure
- Record orientations digitally and check them against daily manpower. Measure: workers on site without orientation.
Next: Permits posted and inspections planned
- 5APM / Project Engineer
Document control setup
Load the current drawing set, configure RFI and submittal workflows, distribution lists and the folder structure.
- Inputs
- Contract documents; Folder template
- Outputs
- Live drawing set; RFI and submittal workflows; Distribution lists
- Done when
- Everyone works from one current set, and the folder structure follows the company template.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Superseded drawings in the field
- Automate and measure
- Create folders and distribution lists from the company template when the job is created. Measure: documents filed outside the standard structure.
Next: Pre-mobilization meetings with trades
- 6Accounting / Finance
Billing and cost setup
Agree the pay app format and cutoff dates, lien waiver rules, retainage, and publish cost coding rules for AP and company cards.
- Inputs
- Contract payment terms; SOV; Cost code list
- Outputs
- Billing calendar; Coding rules published to the team
- Done when
- Every person who spends money on the job knows which codes to use and the cutoff date.
- Typical systems
- Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum); Project management (e.g., Procore, Autodesk Construction Cloud); Spend management (e.g., Ramp)
- Watch for
- Card spend coded to overhead because nobody knew the job codes
- Automate and measure
- Push the job and its active cost codes to the spend management tool so cards can only code to valid lines. Measure: uncoded or miscoded spend in the first month.
Next: Owner preconstruction meeting
- 7Superintendent
Pre-mobilization meetings with trades
Meet each early trade on sequence, logistics, safety, manpower and submittals before they mobilize.
- Inputs
- Schedule; Logistics plan; Subcontract scope
- Outputs
- Trade start dates confirmed; Open questions logged
- Done when
- Each trade leaves with a start date, a foreman name and the site rules.
- Typical systems
- Scheduling (e.g., Primavera P6, Outbuild, Microsoft Project); Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Trades arrive without approved submittals or materials
- Automate and measure
- Send each trade a pre-mobilization packet assembled from the systems. Measure: trades that started on their planned date.
Next: Ready for construction?
- 8Project Manager
Owner preconstruction meeting
Agree with the owner and architect how RFIs, submittals, changes, pay apps and meetings will work.
- Inputs
- PEP; Billing calendar
- Outputs
- Agreed procedures and meeting cadence
- Done when
- Done when the owner has agreed the pay app format, change process and meeting schedule.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive); Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Pay app format disputed at the first billing
- Automate and measure
- Issue meeting minutes and the agreed procedures from one template. Measure: first pay app approved without rework.
Next: Ready for construction?
- 9Operations Support
Permits posted and inspections planned
Post permits on site and set up the inspection plan with the building department and special inspectors.
- Inputs
- Issued permits; Inspection requirements
- Outputs
- Permits posted; Inspection schedule
- Done when
- Every required inspection has an agency and a planned point in the schedule.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Scheduling (e.g., Primavera P6, Outbuild, Microsoft Project)
- Watch for
- Work covered up before an inspection
- Automate and measure
- Add inspection milestones to the schedule and remind the superintendent before each one. Measure: failed or missed inspections.
Next: Ready for construction?
- 10Executive Leadership
Decision: Ready for construction?
Leadership confirms the gate: NTP in hand, plans approved, site ready, systems live.
- Inputs
- Gate checklist; Notice to proceed
- Outputs
- Start of construction, or a list of blockers
- Decision rule
- Start when the NTP is in writing and every gate item is true or has a dated workaround.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Starting without written NTP
- Automate and measure
- Show gate status from live data. Measure: gate items open at start.
Next: Yes → Start construction · No → Project alignment review
- 11Superintendent
Handoff: Start construction
Work begins and the operating rhythm starts: daily huddles, weekly meetings, monthly billing.
- Inputs
- NTP
- Outputs
- Execution under the operating rhythm
- Done when
- The first daily log and the first weekly meeting happen in week one.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Scheduling (e.g., Primavera P6, Outbuild, Microsoft Project)
- Watch for
- Rhythm starts in month two, after the habits are set
- Automate and measure
- Schedule the recurring meetings and reports from the PEP. Measure: routines running in week one.
Roles in this phase
- Executive Leadership
- Confirms readiness and authorizes the start.
- Project Manager
- Runs alignment, writes the PEP, holds the owner precon meeting.
- APM / Project Engineer
- Sets up document control, RFI and submittal workflows.
- Superintendent
- Sets up the site and meets every early trade.
- Operations Support
- Writes the safety plan, posts permits, plans inspections.
- Accounting / Finance
- Sets the billing calendar and publishes cost coding rules.
See the full typical RACI across every phase.
Handoffs in and out
Comes in
- From Preconstruction and procurement: Baseline schedule, subcontracts, permits, logistics plan, submittal register
Goes out
- To Execution: Notice to proceed, PEP, live document control, billing calendar, a running site
- To Finance (continuous): Billing calendar, lien waiver rules and cost coding rules
Gate checklist
Ready for construction (NTP)
Is every system, plan and person in place for day one?
- Notice to proceed received in writing
- Project execution plan written and reviewed with the team
- Site-specific safety plan approved; orientation scheduled
- Temporary facilities, utilities and site protection installed or scheduled
- Document control live: current drawing set, RFI and submittal workflows, distribution lists
- Billing format, cutoff dates and lien waiver rules agreed with the owner and accounting
- Cost coding rules for AP and company cards published to the team
- Required permits posted and inspection agencies identified
Owner: Executive Leadership. Sign-off: Exec, PM, Super.
Common pitfalls
No written NTP
Starting on a verbal go-ahead leaves the schedule and the money exposed.
Coding rules nobody published
If field staff do not know the cost codes, card and invoice spend lands in the wrong place, and month end becomes a re-coding exercise.
Each engineer's own folders
Without a folder template, closeout becomes a search party.
Pay app format agreed late
The first pay app is the worst time to discover the owner wants a different format.
A PEP for the file
If the plan does not name who runs each routine, the routines do not happen.
KPIs to watch
- NTP to first trade
- Calendar days from notice to proceed to the first trade working on site.
- Week-one routines
- Share of PEP routines (daily log, weekly meeting, safety walk) that ran in the first week.
- First-month coding quality
- Uncoded or miscoded spend at the first cutoff.
- First pay app rework
- Revisions requested by the owner on the first pay application.
Definitions for WIP, over/under billing, AR and cash are in the metric dictionary. For the recurring meetings where these get reviewed, see the operating rhythm.
What to automate between systems
Most of the rework in this phase happens where one system hands data to another. Start with the handoff your team re-keys most often.
Job template
Create the folder structure, distribution lists, meeting series and permission groups from a template when the job number is issued.
Cost codes to the spend tool
Sync the job and its active cost codes from the ERP to spend management so card transactions can only be coded to real lines.
Inspection reminders
Inspection milestones in the schedule trigger reminders before work is covered up.
Readiness from live data
Build the ready-for-construction gate from systems of record, not a status email.
Frequently asked questions
What is a project execution plan in construction?
A short document that says how a specific job will be run: the team and responsibilities, communication and meeting cadence, procedures for RFIs, submittals and changes, reporting, and quality and safety requirements.
What is a notice to proceed?
Written authorization from the owner to start work. It usually starts the contract time, so the schedule and any liquidated damages are measured from it.
What should be set up before the first invoice arrives?
The job and cost codes in the accounting system, the same codes in the project management and spend management tools, published coding rules, the billing calendar and cutoff dates, and lien waiver requirements.
Who attends the owner preconstruction meeting?
The owner or their representative, the architect and key consultants, and the GC's PM, superintendent and project engineer. Accounting often joins for the pay application section.
Related on Build Flows
Next step
Want mobilization to run on connected systems?
Tell us which step your team re-keys, chases or rebuilds in a spreadsheet. We'll show you what connecting it would look like and what it would take.
Prefer email? charley@buildflows.ai