Phase 2 of 6 · GC project lifecycle

Contract alignment: turning an award into a budget the books agree with

Award is not the finish line. Between the award notice and the first shovel, the company has to sign a contract it can live with and set the job up so that every later report agrees. This is the phase where the estimate becomes a budget.

Most month-end reporting problems on a job trace back to this phase: a cost code structure that differs between the project management system and the ERP, a schedule of values that does not map to the budget, or a contract value that was typed twice and differs by a change order.

By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC

Purpose
Execute a prime contract with known risk, and create one budget, one schedule of values and one job setup that every system and report will share.
Roles involved
Executive Leadership, Estimating / Preconstruction, Project Manager, Operations Support, Accounting / Finance
Starts with
Estimating and award: Award notice, estimate file, proposal and exclusions
Gate
Contract executed, budget locked

The workflow, animated

Press play to follow the work across roles, or step through it. Select any step for who does it, inputs, outputs, the decision rule, typical systems, common failure points, and what to automate and measure.

1 / 12: Award notice received

Amber boxes are decisions. Dashed shapes are handoffs to another phase. Dashed lines loop back. Roles and steps are typical; adapt them to your company.

Step by step

The 12 steps of contract alignment, in order.

  1. 1Executive Leadership

    Handoff: Award notice received

    A letter of intent or award notice arrives. The award package from estimating comes with it.

    Inputs
    Award notice or letter of intent; Award package from estimating
    Outputs
    Contract review started; Team assigned
    Done when
    Done when a PM is named and the draft contract is in hand.
    Typical systems
    CRM (e.g., HubSpot, Salesforce); Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Starting work on a letter of intent with no limits on spend or scope
    Automate and measure
    Open the contract review checklist and notify accounting to reserve a job number. Measure: days from award to executed contract.

    Next: Contract review · Insurance and bonding review

  2. 2Project Manager

    Contract review

    Compare the contract to the proposal: scope, price, schedule, payment terms, retainage, change process, damages, indemnity.

    Inputs
    Draft prime contract; Proposal and exclusions
    Outputs
    Issues list with proposed language
    Done when
    Every term that differs from the proposal is on the issues list with a recommended position.
    Typical systems
    Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Exclusions from the proposal silently dropped from the contract
    Automate and measure
    Use a clause checklist to flag terms that differ from the company's standard positions. Measure: open contract issues at signing.

    Next: Negotiate exceptions

  3. 3Operations Support

    Insurance and bonding review

    Check the owner's insurance and bond requirements against the company's policies and request bonds.

    Inputs
    Contract insurance exhibit; Current policies
    Outputs
    Gaps identified; Bond request to surety
    Done when
    Done when every required coverage is met or raised as a contract issue.
    Typical systems
    Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Discovering an uninsurable requirement after signing
    Automate and measure
    Compare required limits to a structured policy summary and list the gaps. Measure: days to issue bonds.

    Next: Negotiate exceptions

  4. 4Executive Leadership

    Negotiate exceptions

    Leadership, with counsel where needed, negotiates the issues list with the owner.

    Inputs
    Issues list; Insurance gaps
    Outputs
    Revised contract language
    Done when
    Done when each issue is accepted, revised or consciously left as a known risk.
    Typical systems
    Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Negotiation by email chain with no record of what was agreed
    Automate and measure
    Track each issue's status in one log instead of redlines spread across emails. Measure: issues resolved versus accepted as risk.

    Next: Risk acceptable?

  5. 5Executive Leadership

    Decision: Risk acceptable?

    Leadership decides whether the remaining terms are acceptable for the price.

    Inputs
    Revised contract; Remaining issues
    Outputs
    Approval to sign, or more negotiation
    Decision rule
    Sign when the remaining risk is priced or insured. If not, negotiate again or walk away.
    Typical systems
    Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Signing under schedule pressure with unpriced risk
    Automate and measure
    Summarize open issues and their potential cost on one page for the decision. Measure: contract risk items that later caused a claim.

    Next: Yes → Execute prime contract · No → Negotiate exceptions

  6. 6Executive Leadership

    Execute prime contract

    Sign the contract and send executed copies, certificates and bonds to the owner.

    Inputs
    Final contract; Insurance certificates; Bonds
    Outputs
    Executed contract; Contract value and terms of record
    Done when
    Done when both parties have signed and the executed copy is filed where the team can find it.
    Typical systems
    Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Several versions of the contract in circulation
    Automate and measure
    File the executed contract and push key terms (value, retainage, dates) to the job record. Measure: days from award to execution.

    Next: Estimate to budget · Set up job in the ERP

  7. 7Estimating / Preconstruction

    Estimate to budget

    Convert the estimate into a budget by cost code and cost type, using the company's standard code structure.

    Inputs
    Final estimate; Company cost code list
    Outputs
    Original budget by cost code and cost type
    Done when
    Budget total equals contract value minus fee and contingency, and every line has a valid code.
    Typical systems
    Estimating and takeoff (e.g., takeoff software, HCSS); Spreadsheets (e.g., Excel)
    Watch for
    Estimate categories that do not match the cost codes, so the budget is re-keyed by hand
    Automate and measure
    Map estimate items to cost codes once, in a crosswalk, and export the budget in import format. Measure: budget lines re-coded in the first three months.

    Next: Build the schedule of values

  8. 8Accounting / Finance

    Set up job in the ERP

    Create the job: number, customer, contract value, retainage, billing terms, tax setup and cost code structure.

    Inputs
    Executed contract; Project numbering convention
    Outputs
    Job created in the accounting system
    Done when
    Done when the job number exists and matches the convention every other system will use.
    Typical systems
    Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
    Watch for
    Different job numbers in accounting and in the project management system
    Automate and measure
    Create the job in the PM system from the ERP record, or the other way round, never both by hand. Measure: jobs whose number or name differ between systems.

    Next: Load budget and SOV

  9. 9Project Manager

    Build the schedule of values

    Break the contract value into billable lines the owner approves, mapped to the budget.

    Inputs
    Budget; Owner's SOV requirements
    Outputs
    Schedule of values approved by the owner
    Done when
    Every SOV line maps to one or more budget codes, and the SOV total equals the contract value.
    Typical systems
    Project management (e.g., Procore, Autodesk Construction Cloud); Spreadsheets (e.g., Excel)
    Watch for
    Front-loaded or vague SOV lines that cause pay app disputes
    Automate and measure
    Generate the SOV from the budget roll-up and keep the mapping for billing. Measure: pay app line items disputed by the owner.

    Next: Load budget and SOV

  10. 10Project Manager

    Load budget and SOV

    Load the budget and SOV into the project management system against the same job and codes as the ERP.

    Inputs
    Budget; Approved SOV; ERP job
    Outputs
    Budget and prime contract live in the PM system
    Done when
    Done when both systems show the same contract value and budget total.
    Typical systems
    Project management (e.g., Procore, Autodesk Construction Cloud); Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
    Watch for
    Budget typed into two systems with small differences that surface at WIP
    Automate and measure
    Import the budget into both systems from one file, or sync it through an integration. Measure: budget total difference between systems.

    Next: Systems tie out?

  11. 11Accounting / Finance

    Decision: Systems tie out?

    Accounting checks that contract value, budget total and cost codes agree in every system.

    Inputs
    ERP job; PM system budget and SOV
    Outputs
    Tie-out confirmed, or a fix list
    Decision rule
    Proceed only when the totals match to the dollar. Fix differences now, not at month end.
    Typical systems
    Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum); Project management (e.g., Procore, Autodesk Construction Cloud)
    Watch for
    Skipping the tie-out because the job is about to start
    Automate and measure
    Run a tie-out report that compares the two systems and lists mismatched codes. Measure: days from contract execution to tie-out.

    Next: Yes → Internal turnover meeting · No → Load budget and SOV

  12. 12Project Manager

    Handoff: Internal turnover meeting

    Estimating walks the project team through the estimate, assumptions, risks and sub numbers.

    Inputs
    Estimate file; Contract; Budget
    Outputs
    Turnover notes; Risk register started
    Done when
    Done when the PM and superintendent can explain every major assumption in the price.
    Typical systems
    Files and documents (e.g., SharePoint, OneDrive)
    Watch for
    Turnover skipped, so the team rediscovers the estimate's assumptions the hard way
    Automate and measure
    Use a standard turnover template prefilled from the estimate summary. Measure: turnover meetings held before precon kickoff.

Roles in this phase

Executive Leadership
Negotiates the exceptions, decides on acceptable risk, signs.
Estimating / Preconstruction
Converts the estimate to a budget and explains it at turnover.
Project Manager
Reviews the contract, builds the SOV, loads the budget, runs turnover.
Operations Support
Checks insurance and bonding requirements and requests bonds.
Accounting / Finance
Sets up the job and checks that every system ties out.

See the full typical RACI across every phase.

Handoffs in and out

Comes in

  • From Estimating and award: Award notice, estimate file, proposal and exclusions

Goes out

  • To Preconstruction and procurement: Executed contract, locked budget, approved SOV, turnover notes and risk register
  • To Finance (continuous): Job setup, billing terms, retainage rate and SOV for pay applications

Gate checklist

Contract executed, budget locked

Do the contract, the budget and the books agree?

  • Prime contract executed with exceptions resolved or accepted by leadership
  • Insurance certificates and bonds issued to the owner's requirements
  • Estimate converted into a budget by cost code and cost type
  • Schedule of values approved by the owner and aligned to the cost code structure
  • Job created in the accounting system with contract value, retainage and billing terms
  • Budget and SOV loaded in the project management system with the same job number and codes
  • Budget total ties to contract value minus fee and contingency in both systems
  • Internal turnover meeting held; estimate assumptions handed to the project team

Owner: Project Manager. Sign-off: Exec, PM, Accounting.

Printable version

Common pitfalls

  • Exclusions that disappear

    The proposal excluded it, the contract includes it. Check every exclusion against the final contract.

  • Two cost code structures

    If estimating, the PM system and the ERP use different codes, every report needs a manual crosswalk forever. Decide on one structure here.

  • Budget typed twice

    A budget keyed into two systems will differ. Load from one source.

  • Unmapped schedule of values

    An SOV that does not map to the budget makes over/under billing hard to explain.

  • No turnover

    When estimating and operations do not meet, the field rediscovers the assumptions during buyout.

KPIs to watch

Award to execution
Calendar days from award notice to executed contract.
Tie-out difference
Contract value and budget total difference between the PM system and the ERP. Target: zero.
Budget churn
Budget transfers between cost codes in the first 90 days, as a share of the original budget.
Open contract risks
Issues accepted as known risk at signing, tracked through the job.

Definitions for WIP, over/under billing, AR and cash are in the metric dictionary. For the recurring meetings where these get reviewed, see the operating rhythm.

What to automate between systems

Most of the rework in this phase happens where one system hands data to another. Start with the handoff your team re-keys most often.

  • One budget import

    Export the budget once from estimating in the format both systems accept, or sync it from the ERP to the PM system so there is a single source.

  • Job creation sync

    Create the job once and replicate it, so job numbers, names and customers match everywhere.

  • Cost code crosswalk

    Keep the mapping between estimate items, cost codes and SOV lines in one table that every report uses.

  • Automatic tie-out

    A scheduled check that compares contract value, budget and codes across systems and alerts on any difference.

Frequently asked questions

What is a schedule of values?

The schedule of values breaks the contract sum into line items the owner agrees to, used to measure progress and bill each month. It should map to the internal budget so billing and cost can be compared.

How do you convert an estimate into a construction budget?

Map each estimate item to the company's cost codes and cost types, separate fee and contingency, and check that the budget total plus fee and contingency equals the contract value. Load the result into both the project management system and the accounting system from the same file.

Why should the PM system and the ERP use the same cost codes?

Because every cost report, forecast and WIP calculation joins the two. Different codes mean someone translates by hand every month, and the translation is where errors live.

What is an internal turnover meeting?

A meeting where estimating hands the job to the project team: the estimate, its assumptions, sub numbers, plugs, risks and the promises made in the proposal.

Next step