Phase 2 of 6 · GC project lifecycle
Contract alignment: turning an award into a budget the books agree with
Award is not the finish line. Between the award notice and the first shovel, the company has to sign a contract it can live with and set the job up so that every later report agrees. This is the phase where the estimate becomes a budget.
Most month-end reporting problems on a job trace back to this phase: a cost code structure that differs between the project management system and the ERP, a schedule of values that does not map to the budget, or a contract value that was typed twice and differs by a change order.
By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC
- Purpose
- Execute a prime contract with known risk, and create one budget, one schedule of values and one job setup that every system and report will share.
- Roles involved
- Executive Leadership, Estimating / Preconstruction, Project Manager, Operations Support, Accounting / Finance
- Starts with
- Estimating and award: Award notice, estimate file, proposal and exclusions
- Gate
- Contract executed, budget locked
The workflow, animated
Press play to follow the work across roles, or step through it. Select any step for who does it, inputs, outputs, the decision rule, typical systems, common failure points, and what to automate and measure.
1 / 12: Award notice received
Handoff 1 of 12 · Executive Leadership
Award notice received
A letter of intent or award notice arrives. The award package from estimating comes with it.
- Who
- Executive Leadership
- Inputs
- Award notice or letter of intent; Award package from estimating
- Outputs
- Contract review started; Team assigned
- Done when
- Done when a PM is named and the draft contract is in hand.
- Common failure points
- Starting work on a letter of intent with no limits on spend or scope
- What to automate
- Open the contract review checklist and notify accounting to reserve a job number.
- What to measure
- Days from award to executed contract
Tap a step for its details.
Amber boxes are decisions. Dashed shapes are handoffs to another phase. Dashed lines loop back. Roles and steps are typical; adapt them to your company.
Step by step
The 12 steps of contract alignment, in order.
- 1Executive Leadership
Handoff: Award notice received
A letter of intent or award notice arrives. The award package from estimating comes with it.
- Inputs
- Award notice or letter of intent; Award package from estimating
- Outputs
- Contract review started; Team assigned
- Done when
- Done when a PM is named and the draft contract is in hand.
- Typical systems
- CRM (e.g., HubSpot, Salesforce); Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Starting work on a letter of intent with no limits on spend or scope
- Automate and measure
- Open the contract review checklist and notify accounting to reserve a job number. Measure: days from award to executed contract.
Next: Contract review · Insurance and bonding review
- 2Project Manager
Contract review
Compare the contract to the proposal: scope, price, schedule, payment terms, retainage, change process, damages, indemnity.
- Inputs
- Draft prime contract; Proposal and exclusions
- Outputs
- Issues list with proposed language
- Done when
- Every term that differs from the proposal is on the issues list with a recommended position.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Exclusions from the proposal silently dropped from the contract
- Automate and measure
- Use a clause checklist to flag terms that differ from the company's standard positions. Measure: open contract issues at signing.
Next: Negotiate exceptions
- 3Operations Support
Insurance and bonding review
Check the owner's insurance and bond requirements against the company's policies and request bonds.
- Inputs
- Contract insurance exhibit; Current policies
- Outputs
- Gaps identified; Bond request to surety
- Done when
- Done when every required coverage is met or raised as a contract issue.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Discovering an uninsurable requirement after signing
- Automate and measure
- Compare required limits to a structured policy summary and list the gaps. Measure: days to issue bonds.
Next: Negotiate exceptions
- 4Executive Leadership
Negotiate exceptions
Leadership, with counsel where needed, negotiates the issues list with the owner.
- Inputs
- Issues list; Insurance gaps
- Outputs
- Revised contract language
- Done when
- Done when each issue is accepted, revised or consciously left as a known risk.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Negotiation by email chain with no record of what was agreed
- Automate and measure
- Track each issue's status in one log instead of redlines spread across emails. Measure: issues resolved versus accepted as risk.
Next: Risk acceptable?
- 5Executive Leadership
Decision: Risk acceptable?
Leadership decides whether the remaining terms are acceptable for the price.
- Inputs
- Revised contract; Remaining issues
- Outputs
- Approval to sign, or more negotiation
- Decision rule
- Sign when the remaining risk is priced or insured. If not, negotiate again or walk away.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Signing under schedule pressure with unpriced risk
- Automate and measure
- Summarize open issues and their potential cost on one page for the decision. Measure: contract risk items that later caused a claim.
Next: Yes → Execute prime contract · No → Negotiate exceptions
- 6Executive Leadership
Execute prime contract
Sign the contract and send executed copies, certificates and bonds to the owner.
- Inputs
- Final contract; Insurance certificates; Bonds
- Outputs
- Executed contract; Contract value and terms of record
- Done when
- Done when both parties have signed and the executed copy is filed where the team can find it.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Several versions of the contract in circulation
- Automate and measure
- File the executed contract and push key terms (value, retainage, dates) to the job record. Measure: days from award to execution.
Next: Estimate to budget · Set up job in the ERP
- 7Estimating / Preconstruction
Estimate to budget
Convert the estimate into a budget by cost code and cost type, using the company's standard code structure.
- Inputs
- Final estimate; Company cost code list
- Outputs
- Original budget by cost code and cost type
- Done when
- Budget total equals contract value minus fee and contingency, and every line has a valid code.
- Typical systems
- Estimating and takeoff (e.g., takeoff software, HCSS); Spreadsheets (e.g., Excel)
- Watch for
- Estimate categories that do not match the cost codes, so the budget is re-keyed by hand
- Automate and measure
- Map estimate items to cost codes once, in a crosswalk, and export the budget in import format. Measure: budget lines re-coded in the first three months.
Next: Build the schedule of values
- 8Accounting / Finance
Set up job in the ERP
Create the job: number, customer, contract value, retainage, billing terms, tax setup and cost code structure.
- Inputs
- Executed contract; Project numbering convention
- Outputs
- Job created in the accounting system
- Done when
- Done when the job number exists and matches the convention every other system will use.
- Typical systems
- Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
- Watch for
- Different job numbers in accounting and in the project management system
- Automate and measure
- Create the job in the PM system from the ERP record, or the other way round, never both by hand. Measure: jobs whose number or name differ between systems.
Next: Load budget and SOV
- 9Project Manager
Build the schedule of values
Break the contract value into billable lines the owner approves, mapped to the budget.
- Inputs
- Budget; Owner's SOV requirements
- Outputs
- Schedule of values approved by the owner
- Done when
- Every SOV line maps to one or more budget codes, and the SOV total equals the contract value.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Spreadsheets (e.g., Excel)
- Watch for
- Front-loaded or vague SOV lines that cause pay app disputes
- Automate and measure
- Generate the SOV from the budget roll-up and keep the mapping for billing. Measure: pay app line items disputed by the owner.
Next: Load budget and SOV
- 10Project Manager
Load budget and SOV
Load the budget and SOV into the project management system against the same job and codes as the ERP.
- Inputs
- Budget; Approved SOV; ERP job
- Outputs
- Budget and prime contract live in the PM system
- Done when
- Done when both systems show the same contract value and budget total.
- Typical systems
- Project management (e.g., Procore, Autodesk Construction Cloud); Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum)
- Watch for
- Budget typed into two systems with small differences that surface at WIP
- Automate and measure
- Import the budget into both systems from one file, or sync it through an integration. Measure: budget total difference between systems.
Next: Systems tie out?
- 11Accounting / Finance
Decision: Systems tie out?
Accounting checks that contract value, budget total and cost codes agree in every system.
- Inputs
- ERP job; PM system budget and SOV
- Outputs
- Tie-out confirmed, or a fix list
- Decision rule
- Proceed only when the totals match to the dollar. Fix differences now, not at month end.
- Typical systems
- Accounting / ERP (e.g., Sage, Viewpoint Vista, Spectrum); Project management (e.g., Procore, Autodesk Construction Cloud)
- Watch for
- Skipping the tie-out because the job is about to start
- Automate and measure
- Run a tie-out report that compares the two systems and lists mismatched codes. Measure: days from contract execution to tie-out.
Next: Yes → Internal turnover meeting · No → Load budget and SOV
- 12Project Manager
Handoff: Internal turnover meeting
Estimating walks the project team through the estimate, assumptions, risks and sub numbers.
- Inputs
- Estimate file; Contract; Budget
- Outputs
- Turnover notes; Risk register started
- Done when
- Done when the PM and superintendent can explain every major assumption in the price.
- Typical systems
- Files and documents (e.g., SharePoint, OneDrive)
- Watch for
- Turnover skipped, so the team rediscovers the estimate's assumptions the hard way
- Automate and measure
- Use a standard turnover template prefilled from the estimate summary. Measure: turnover meetings held before precon kickoff.
Roles in this phase
- Executive Leadership
- Negotiates the exceptions, decides on acceptable risk, signs.
- Estimating / Preconstruction
- Converts the estimate to a budget and explains it at turnover.
- Project Manager
- Reviews the contract, builds the SOV, loads the budget, runs turnover.
- Operations Support
- Checks insurance and bonding requirements and requests bonds.
- Accounting / Finance
- Sets up the job and checks that every system ties out.
See the full typical RACI across every phase.
Handoffs in and out
Comes in
- From Estimating and award: Award notice, estimate file, proposal and exclusions
Goes out
- To Preconstruction and procurement: Executed contract, locked budget, approved SOV, turnover notes and risk register
- To Finance (continuous): Job setup, billing terms, retainage rate and SOV for pay applications
Gate checklist
Contract executed, budget locked
Do the contract, the budget and the books agree?
- Prime contract executed with exceptions resolved or accepted by leadership
- Insurance certificates and bonds issued to the owner's requirements
- Estimate converted into a budget by cost code and cost type
- Schedule of values approved by the owner and aligned to the cost code structure
- Job created in the accounting system with contract value, retainage and billing terms
- Budget and SOV loaded in the project management system with the same job number and codes
- Budget total ties to contract value minus fee and contingency in both systems
- Internal turnover meeting held; estimate assumptions handed to the project team
Owner: Project Manager. Sign-off: Exec, PM, Accounting.
Common pitfalls
Exclusions that disappear
The proposal excluded it, the contract includes it. Check every exclusion against the final contract.
Two cost code structures
If estimating, the PM system and the ERP use different codes, every report needs a manual crosswalk forever. Decide on one structure here.
Budget typed twice
A budget keyed into two systems will differ. Load from one source.
Unmapped schedule of values
An SOV that does not map to the budget makes over/under billing hard to explain.
No turnover
When estimating and operations do not meet, the field rediscovers the assumptions during buyout.
KPIs to watch
- Award to execution
- Calendar days from award notice to executed contract.
- Tie-out difference
- Contract value and budget total difference between the PM system and the ERP. Target: zero.
- Budget churn
- Budget transfers between cost codes in the first 90 days, as a share of the original budget.
- Open contract risks
- Issues accepted as known risk at signing, tracked through the job.
Definitions for WIP, over/under billing, AR and cash are in the metric dictionary. For the recurring meetings where these get reviewed, see the operating rhythm.
What to automate between systems
Most of the rework in this phase happens where one system hands data to another. Start with the handoff your team re-keys most often.
One budget import
Export the budget once from estimating in the format both systems accept, or sync it from the ERP to the PM system so there is a single source.
Job creation sync
Create the job once and replicate it, so job numbers, names and customers match everywhere.
Cost code crosswalk
Keep the mapping between estimate items, cost codes and SOV lines in one table that every report uses.
Automatic tie-out
A scheduled check that compares contract value, budget and codes across systems and alerts on any difference.
Frequently asked questions
What is a schedule of values?
The schedule of values breaks the contract sum into line items the owner agrees to, used to measure progress and bill each month. It should map to the internal budget so billing and cost can be compared.
How do you convert an estimate into a construction budget?
Map each estimate item to the company's cost codes and cost types, separate fee and contingency, and check that the budget total plus fee and contingency equals the contract value. Load the result into both the project management system and the accounting system from the same file.
Why should the PM system and the ERP use the same cost codes?
Because every cost report, forecast and WIP calculation joins the two. Different codes mean someone translates by hand every month, and the translation is where errors live.
What is an internal turnover meeting?
A meeting where estimating hands the job to the project team: the estimate, its assumptions, sub numbers, plugs, risks and the promises made in the proposal.
Related on Build Flows