GC project lifecycle · printable
Construction project gates and checklists
Seven gates move a commercial job from pursuit to a closed file. Each one is a short list of things that must be true before the job moves on, with an owner who signs off. Tick them on screen or print the page for your next kickoff or review meeting.
These are typical checklists. Add the items your contracts and your company require.
By Charley Forey, Build Flows · Published November 19, 2026 · Typical practice, generalized for any commercial GC
Prints one gate per block, without the site navigation. Ticks are not saved.
Build Flows · GC project gate checklists
The gate checklists
Gate 1 · Phase 1: Estimating and award
Go / no-go to pursue
Is this a job we should spend estimating hours on?
- Owner
- Executive Leadership
- Sign-off
- Executive Leadership, Estimating / Preconstruction
- Signed / date
Gate 2 · Phase 1: Estimating and award
Bid approval
Is the price complete, covered, and worth the risk?
- Owner
- Executive Leadership
- Sign-off
- Executive Leadership, Estimating / Preconstruction, Project Manager
- Signed / date
Gate 3 · Phase 2: Contract alignment
Contract executed, budget locked
Do the contract, the budget and the books agree?
- Owner
- Project Manager
- Sign-off
- Executive Leadership, Project Manager, Accounting / Finance
- Signed / date
Gate 4 · Phase 3: Preconstruction and procurement
Ready to mobilize
Can we put people on site without stopping in week two?
- Owner
- Project Manager
- Sign-off
- Project Manager, Superintendent, Operations Support
- Signed / date
Gate 5 · Phase 4: Mobilization
Ready for construction (NTP)
Is every system, plan and person in place for day one?
- Owner
- Executive Leadership
- Sign-off
- Executive Leadership, Project Manager, Superintendent
- Signed / date
Gate 6 · Phase 5: Execution operating rhythm
Substantial completion
Can the owner use the building for its intended purpose?
- Owner
- Project Manager
- Sign-off
- Project Manager, Superintendent, Executive Leadership
- Signed / date
Gate 7 · Phase 6: Handover and closeout
Financial closeout
Is every dollar billed, paid, released and explained?
- Owner
- Accounting / Finance
- Sign-off
- Accounting / Finance, Project Manager, Executive Leadership
- Signed / date
Running a gate review
- Send the checklist with live status a day before. Nobody should learn the status in the meeting.
- Review only the items that are not true. For each, decide: fix before moving on, or move on with a dated workaround and an owner.
- Record the decision and the sign-offs where the team can find them later.
- After the project, add the items you wish you had checked.
Frequently asked questions
What is a stage gate in construction?
A point between phases where a short checklist must be true before the job moves on, with a named owner who signs off. Gates catch missing items while they are still cheap to fix.
How many gates should a construction project have?
Enough to cover the expensive handoffs and no more. Seven is a common pattern for a commercial GC: pursue, bid approval, contract and budget, ready to mobilize, ready for construction, substantial completion and financial closeout.
Who signs off a gate?
One accountable owner, usually the PM or an executive, with sign-off from the roles who will live with the result. Accounting should sign the contract-and-budget gate and the financial closeout gate.
Can gate status come from our systems instead of a meeting?
Most of it can. Contract value, budget tie-out, commitments, compliance documents, permits, punch lists and open changes all live in the project management and accounting systems. A gate report built from them turns the meeting into a review of exceptions.
Related on Build Flows
Next step
Want gate status built from your systems?
Contract value, budget tie-out, commitments, compliance, permits and punch lists already live in your systems. We can turn them into a live gate report.
Prefer email? charley@buildflows.ai