What Good Looks Like: A Starter KPI Scorecard for a Small GC

A starter KPI scorecard for a small GC, built from a discovery call with Cattlemen Construction Services: 12 KPIs in four groups (Money, Delivery, Field discipline, Admin), each with a definition, source system, formula, default green/amber/red tolerance and reason. Covers standardizing Procore inputs first, scoring weekly, validating each number against its source of truth, role-based views, tuning tolerances after 4-6 weeks and using red tiles to ask what happened rather than to punish.

By Charley Forey, founder of Build Flows

Key takeaways

  • Start with 12 KPIs in four groups: Money, Delivery, Field discipline and Admin. Add more only after the first month.
  • Every KPI needs a definition, a source system, a formula and a green/amber/red tolerance. The defaults here are starting points, not industry standards.
  • Standardize inputs before you score. If daily logs are skipped or card spend never reaches Procore, the scorecard is accurate and useless.
  • Score weekly against a fixed cutoff, and show on every tile where the number came from and how many validation checkpoints it passed.
  • Make views role-based: superintendents and PMs see their projects, executives see everything, accounting owns the coding queue.
  • Run the defaults unchanged for 4-6 weeks, then reset bands around how your well-run projects actually perform.
  • Treat red as "what happened here?" Punishing red tiles makes people game the inputs.

29 seconds · From a Build Flows walkthrough

"I know what good feels like, but I couldn't tell you how to measure it"

Start from an out-of-the-box KPI set and adjust the tolerances to how your best jobs actually run.

Read the clip transcript

sign in so it's just it's behind some type of access privilege I wouldn't even be able to really tell you what good looks like right now like I know it I know it in my brain like I know what good feels like but I couldn't tell you how to measure it and so I would be curious if you were ever to like white label that would we almost just be able to come out of the box of whatever you [—] kind of saying hey this is how we what we care about and then I can I can you know adjust my tolerances from there so that it it goes yeah I mean I'd be happy to

Captions adapted from the source video; proper names may reflect automatic transcription. Original segment: 26:52–27:21. Watch at the source.

40 seconds · From a Build Flows walkthrough

The executive panel: cash, owed, billing position, not in Procore

Month, quarter, year or trailing 12: cash, receivables, billing position, spend not yet in Procore, backlog, revenue, margin and pending change orders.

Read the clip transcript

This then goes into the company details. So this company detail is just a general overarching executive panel of what they would see. And so you can dive into a month to date, quarter, year, or the trailing 12. And this essentially pulls in all of the cash balance, what's owed, billing positions, what's not in Procore. So this would be what still needs to be assigned from QuickBooks and be able to be provisioned to the correct coding structure, any backlog, revenue, gross margin, change orders that are pending, and then some graphs and charts to be able to track and analyze everything with alerts that are over here as well that we'll dive into shortly.

Captions adapted from the source video; proper names may reflect automatic transcription. Original segment: 19:15–19:55. Watch at the source.

Near the end of our discovery call with Cattlemen Construction Services, a young GC and design-build firm in Fort Worth, Texas, co-founder Ryan Blankers said something most small-GC owners would recognize:

"I couldn't tell you what good looks like right now. I know what good feels like, but I couldn't tell you how to measure it."

He wasn't asking for a hundred metrics. He wanted an out-of-the-box set he could switch on, with tolerances he could adjust once he'd lived with them. This guide is that starter set: 12 KPIs in four groups, each with a definition, the system it comes from, a formula, a default green/amber/red band and a reason it earns a place. It also covers the part that decides whether any scorecard works, which is the inputs.

The call itself was mostly about getting Ramp card spend into Procore job costs. That story is in the call walkthrough, and you can watch the recording on the video page. Two of the KPIs below exist because of that gap.

A sample weekly scorecard for a fictional company, Sample Builders. Four groups of tiles, Money, Delivery, Field discipline and Admin, each tile colored green, amber or red. A note says every tile shows where its number came from.A starter scorecard: 12 KPIs, four groups, one color each

Start with the inputs

The analysis is only as good as the inputs. Charley said it on the call, and it's the most common reason dashboards get ignored. If half the superintendents skip the daily log, a "daily log completion" tile is accurate and useless. If card spend never reaches Procore, a cost-to-complete number in Procore is wrong before anyone looks at it.

So the order is:

  1. Standardize the inputs. Decide which fields must be filled in Procore every week (daily logs, RFI due dates, change event status, projected cost to complete) and who owns each. Ryan called Procore his "vehicle, my Trojan horse": everyone loads into Procore, and Procore feeds the dashboard and the AI layer.
  2. Score weekly. Same cutoff every week, for example Friday at noon. A KPI that moves daily invites noise. One that moves monthly hides problems for too long.
  3. Validate every number against its source of truth. Each tile should say where it was pulled from and which checks it passed.

A loop with three stages. Inputs: Procore fields filled weekly, Ramp expenses coded, QuickBooks reconciled. Score: the Friday cutoff calculates 12 KPIs and colors them against tolerances. Validate: each number is checked against its source, for example 3 of 5 checkpoints passed with links to where it was pulled. Arrows return to inputs, where the fixes happen.Inputs, score, validate, then back to inputs

The starter set

Twelve KPIs, scored per project and rolled up to the company. Every tolerance below is a default to start from. None of them is an industry standard, and you should expect to move most of them.

Money

KPISourceFormulaGreen / Amber / RedWhy it matters
Card spend coded to a cost codeRamp, QuickBooks Online, ProcoreJob-related card spend with a Procore cost code ÷ all job-related card spend, last 30 days. Show the uncoded dollars and count next to it.≥ 95% / 85-95% / < 85%Uncoded spend is cost the PM can't see. On Cattlemen's setup it landed in QuickBooks but showed $0 in Procore.
Cost-to-complete varianceProcore budget(Projected cost at completion − revised budget) ÷ revised budget≤ 2% over / 2-5% over / > 5% overThe earliest warning of fade. Also watch the week-over-week change: a jump with no change order is a question.
Billed vs earned (over/under billing)QuickBooks Online (billed), Procore (cost, budget)Billed to date − (percent complete × contract value), where percent complete = cost to date ÷ projected cost at completion. Show as % of contract.Within ±3% / ±3-7% / beyond ±7%Over-billing borrows from the end of the job. Under-billing finances the owner. Both distort cash.
AR over 60 daysQuickBooks Online (A/R aging)Receivables more than 60 days past invoice ÷ total receivables< 10% / 10-25% / > 25%Cash position is the company-level result of the other three. Pair it with cash on hand vs the next four weeks of payables.

If over/under billing is new to you, our WIP explainer walks through the math with worked examples.

Delivery

KPISourceFormulaGreen / Amber / RedWhy it matters
Schedule varianceProject schedule (Procore or your scheduling tool)Forecast substantial completion − contract or baseline substantial completion, in working days≤ 5 days late / 6-15 / > 15Late finishes cost general conditions and owner goodwill. Track the trend, not just the number.
Overdue RFIs and submittalsProcore RFIs and SubmittalsOpen items past their due date, per project0-2 / 3-5 / > 5Overdue answers become field delays two to four weeks later. Also a fair read of design team responsiveness.
Change order cycle timeProcore change events and change ordersMedian days from change event created to owner-executed change order, items closed in last 90 days≤ 14 days / 15-30 / > 30Work done ahead of a signed change order is unbilled, unprotected work.

Field discipline

KPISourceFormulaGreen / Amber / RedWhy it matters
Daily logs submittedProcore Daily LogWorkdays with a completed daily log ÷ workdays on site, last 7 days≥ 95% / 80-95% / < 80%Daily logs are your record for delay claims and disputes, and the input for most field metrics.
Inspections completed on timeProcore InspectionsInspections closed by their due date ÷ inspections due, last 14 days≥ 90% / 75-90% / < 75%Missed inspections show up later as rework, punch items or a failed city inspection.
Meeting notes out before the OACProcore MeetingsOwner-architect-contractor (OAC) meetings where the prior minutes were distributed at least 2 business days ahead ÷ OAC meetings held, last 4100% / one late / two or more late or missingMinutes that arrive late don't get read, and action items roll forward unowned.

Admin

KPISourceFormulaGreen / Amber / RedWhy it matters
Days to code card spendRamp, expense coding portalMedian days from card transaction to cost code approved, last 30 days≤ 3 days / 4-7 / > 7Coding gets harder every day the receipt ages. This is the leading indicator for the first Money KPI.
Costs visible in ProcoreQuickBooks Online, ProcoreJob cost dollars in Procore ÷ job cost dollars in QuickBooks for the same jobs and period≥ 98% / 90-98% / < 90%The tie-out between accounting and project management. If it's red, every Procore-based Money KPI is suspect.

That's 12. Add your own only after these have run for a month. A short list people look at beats a long one they skim.

A sample scorecard for job 24-017 Sample Retail TI at Sample Builders. Twelve tiles in four rows. Money: card spend coded 92 percent amber, cost-to-complete variance 1.4 percent green, billed vs earned plus 4.1 percent amber, AR over 60 days 8 percent green. Delivery: schedule variance 3 days green, overdue RFIs and submittals 6 red, change order cycle time 19 days amber. Field discipline: daily logs 100 percent green, inspections 88 percent amber, meeting notes on time green. Admin: days to code 5 amber, costs visible in Procore 97 percent amber.Fake data: what one project's week looks like

Validate each number against its source

A scorecard loses trust the first time someone finds a wrong number on it. The fix is to show the receipts. Every tile carries a short list of checkpoints and the result, for example "3 of 5 checkpoints passed", with a link to each place the data was pulled from.

Typical checkpoints:

CheckpointExample for "Costs visible in Procore"
FreshQuickBooks and Procore pulls both ran after Friday's cutoff
CompleteEvery active job in Procore has a matching QuickBooks project
Ties to sourceProcore job cost total matches the Procore budget report for the job
Ties across systemsQuickBooks job cost total matches the profit and loss by project report for the same dates
Required fieldsNo expense line on the job is missing a cost code or class

When a tile passes 3 of 5, you show the number with the two failed checks next to it. People can decide how much to trust it, and the failed checks become the input fixes for next week.

Who sees what

Scorecards are role-based, the same way Ryan described the dashboard he wants:

  • Superintendents and PMs see their own projects, with the field discipline and delivery KPIs up front.
  • Executives see every project and the company roll-up, with the Money group first.
  • Accounting or a controller sees the Admin group across all jobs, because they own the coding queue.

Roles should come from the same identity the team already signs in with, so access follows the person when they change projects. If you plan to let an AI assistant answer questions from the same data, the same rules have to apply to it. We cover that in plugging your dashboard into an AI assistant.

Tune tolerances after 4-6 weeks

The defaults above will be wrong for your company in a few places, and you won't know which until you've seen real weeks.

A dial for one KPI, days to code card spend. Green runs to 3 days, amber 4 to 7, red beyond 7. A needle sits at 5. A note says to move the bands after 4 to 6 weekly scores, based on what your well-run projects actually do.Each tolerance is a setting you can move

A simple method:

  1. Run the scorecard for 4 to 6 weeks without changing anything.
  2. For each KPI, look at the projects you'd call well run. Where do they sit?
  3. Set green to cover them, amber to cover a normal bad week, and red for the weeks where you'd want a phone call.
  4. Write down each change and the reason. Review the bands every quarter.

If a KPI is red on every project every week, either the tolerance is wrong or the input is broken. Check the validation checkpoints before you adjust the band.

Use red to ask questions

A red tile is the start of a conversation: "what happened here?" Maybe the RFIs are overdue because the architect is slow, and the right action is to escalate with the design team. Maybe card spend is uncoded because a new superintendent never got a login to the coding portal.

If people get punished for red, the inputs start to drift. Daily logs get filled in with "same as yesterday", projected costs stop moving, and the scorecard turns green while the jobs don't. Ryan's stated goal was to automate "so that we can hire performers rather than administrators." The scorecard supports that only if performers trust it.

A weekly rhythm that works for a small GC:

WhenWhoWhat
Friday noonSystemCutoff, pulls from Procore, QuickBooks and Ramp, checkpoints run
Friday afternoonControllerClears the coding queue, reviews the Admin group
MondayEach PMReviews their projects, adds a one-line note to any red tile
Monday or TuesdayOwners20 minutes on the company view, picks two reds to follow up

Where the card spend KPIs come from

Two of the 12 KPIs depend on card spend reaching Procore. At Cattlemen, Ramp syncs expenses to QuickBooks Online on account-based category lines, and Procore's QuickBooks integration brings in item-based lines tied to cost codes, so those costs showed $0 in Procore. The fix we agreed on was a small expense coding portal where each cardholder picks the cost code and one person controls the approvals. Once it runs, "card spend coded" and "days to code" come straight out of the portal's queue.

The same standardize-first thinking applies to documents. A flat, numbered SharePoint project folder structure is what lets a dashboard link each project to its files.

Checklist

  • Weekly input fields agreed in Procore, with an owner for each
  • Friday cutoff time set
  • 12 KPIs configured with the default tolerances
  • Source and checkpoints listed on every tile
  • Roles mapped: field and PMs to their projects, executives to all
  • Card spend flowing to Procore job costs before Money KPIs are trusted
  • Tolerance review booked for week 6
  • Rule written down: red means "what happened here?"

Want a scorecard like this on your jobs?

Build Flows builds role-based operating dashboards for contractors on top of Procore, QuickBooks and Ramp, starting from this KPI set and tuning it with you. Email charley@buildflows.ai or tell us what you're building.

Frequently asked questions

What KPIs should a small general contractor track?

A workable starter set is 12 KPIs in four groups. Money: card spend coded to a cost code, cost-to-complete variance, billed vs earned, and AR over 60 days. Delivery: schedule variance, overdue RFIs and submittals, and change order cycle time. Field discipline: daily logs submitted, inspections on time, and meeting notes out before the OAC. Admin: days to code card spend and percent of costs visible in Procore.

How do I set green, amber and red tolerances for construction KPIs?

Start with default bands, run them unchanged for 4 to 6 weekly scores, then look at where your well-run projects sit. Set green to cover them, amber for a normal bad week and red for weeks that deserve a phone call. Write down each change and the reason, and review the bands quarterly.

How is billed vs earned (over/under billing) calculated?

Earned revenue is percent complete times contract value, where percent complete is cost to date divided by projected cost at completion. Over or under billing is billed to date minus earned revenue. On a scorecard, show it as a percentage of contract value so jobs of different sizes compare.

Where does the data for a GC KPI scorecard come from?

Mostly Procore (budget, projected costs, RFIs, submittals, change orders, daily logs, inspections, meetings) and QuickBooks Online (billing, A/R aging, job cost totals). Card spend metrics come from Ramp and the expense coding workflow that gets those costs into Procore.

How often should a construction KPI scorecard be updated?

Weekly, at the same cutoff each week, such as Friday at noon. Daily scores invite noise and monthly scores hide problems for too long.

How do I know the numbers on the scorecard are right?

Validate each KPI against its source of truth with a short list of checkpoints, such as data freshness, completeness, ties to the source report and ties across systems. Show the result on the tile, for example 3 of 5 checkpoints passed, with links to where each value was pulled.

Next step

Trying to automate a report like this?

Discuss your current reporting process: what the team does today, which systems are involved, and what you want to change.

Prefer email? charley@buildflows.ai

Keep learning

Integrations · November 18, 2026

Why Ramp Card Costs Show $0 in Procore: A Real Discovery Call, Walked Through

A walkthrough of a recorded discovery call with Ryan Blankers of Cattlemen Construction Services in Fort Worth, Texas. Ramp card expenses sync to QuickBooks Online as Category details lines, while Procore's QuickBooks integration builds job costs from Item details lines tied to a cost code, so card spend shows $0 in Procore. Covers why the fix can't be fully automatic, the expense coding portal design with approvals and an audit log, the GL to cost code mapping, hosting, a role-based Cattlemen OS with KPIs, SharePoint project folders and a Procore convert-to-won automation, embedding into an AI platform through an iframe, API or MCP server, and the timeline.

Integrations · November 18, 2026

Design a Human-in-the-Loop Expense Coding Portal for Ramp, QuickBooks and Procore

The expense coding portal designed on a recorded discovery call with Cattlemen Construction Services. Cardholders sign in and see only their uncoded card expenses, pick a suggested Procore cost code and approve; the portal rebuilds the QuickBooks Online expense with Item details and Procore's own integration brings it in as actual cost. Covers the admin view, notifications, roles, audit log, failure handling, idempotency, API scopes, hosting, the proof of concept and the metrics that show it's working.

Reporting & analytics · October 10, 2026

Over/Under Billing Explained: How to Read Your WIP Schedule

How over and under billing are calculated, three worked jobs including a stale forecast, the month-end journal entries and balance sheet impact, the usual causes, and a routine to review the WIP schedule every close.