Key takeaways
- A grade is 100 times the sum of pillar weight times pillar score, divided by the weights of pillars with data, so missing data drops out instead of dragging the grade down.
- Each measure turns a reading into a 0-1 score through bands an executive can edit; some bands have deliberate cliffs, such as cost coding below 80% scoring zero.
- Default tolerances: 90 and up on track, 75 to 89 monitor, under 75 needs attention, and unscored when less than 50% of the weight has data.
- Sample job 26-004 grades 79.5: schedule 0.933, financials 0.613, safety 0.84, quality 0.82, controls 0.77, with financials the weakest pillar at 7.7 points lost.
- Moving Financials to 40% and the rest to 15% drops 26-004 to 74.98 and into needs attention; a live what-if shows this before anything is saved.
- Many measures reward inputs (a current look-ahead, daily logs, coded card spend), which is how a grade standardizes the data the money numbers depend on.
58 seconds · From a Build Flows walkthrough
Project grades and scorecards
Each project gets a grade from weighted measures like schedule, cost, cash and data quality, so leaders can rank jobs and reward the teams behind them.
Read the clip transcript
We give a general overarching project ranking and grades for all of this as well. So each of these projects we can drill down that we showed previously, but then these have grades. So as these projects are progressing, we'll see now here that project is underway and that we have all of our contracts and what we've built, our costs that we've done, and any revisions and then we can start seeing the grading system for how on track it is, any coverages. I'm working with clients as well that are giving to grading rubrics and quality scores for how their team is leveraging and putting data into Procore or their respective system, or how, you know, strong their cash position is against a project or how much they're collecting or what's outstanding and then they give specific scores and percentages and be able to then rank these projects and be able to assign a proper score to be able to give prizes or be able to rank them for better visibility into how it's progressing but then ultimately we can
Captions adapted from the source video; proper names may reflect automatic transcription. Original segment: 19:55–20:53. Watch at the source.
A project grade is one number from 0 to 100 for each job, built from weighted pillars: schedule, financials, safety, quality and project controls. Each pillar is built from measures you can check against Procore, QuickBooks or the app's own coding log, and each measure is scored against bands an executive can change. This guide explains the grade we built into the Cattlemen OS proof of concept for Cattlemen Construction Services: the metric definitions, the bands and tolerances, the math, a full worked example on a sample job, and what happens when an executive moves the weights. A scorecard template (CSV) with every measure, band and three graded sample jobs is at the end.
A grade is five pillars, weighted
Ryan Blankers, Cattlemen's co-founder, described the problem on our first call: "I couldn't tell you what good looks like right now. I know what good feels like, but I couldn't tell you how to measure it." The grade is our answer. It starts from a sensible default, it's honest about missing data, and it lets the partners change what "good" means as they learn their numbers. You can watch the walkthrough; the ranking and grade screens run from about 19:55 to 20:55.
Why one number per job
Most contractors already have a dozen KPIs. The trouble is reading them across 8 or 20 jobs at once. A grade does three things a KPI list doesn't:
- It ranks. The company dashboard lists jobs best first, so the partners know which two jobs to ask about on Monday.
- It explains itself. Every grade breaks down into pillars, measures, readings and bands. Nobody has to trust a black box.
- It points at the weakest pillar. The pillar costing the most points is named on the card, so the question is specific: "Why is Financials at 61% on Clearfork?"
The grade is a way to ask better questions. It's not a performance review. We say that to every client, because a grade that's used to punish PMs gets gamed in a month.
The pillars and their measures
The default setup has five weighted pillars and one switched off.
| Pillar | Default weight | What it asks |
|---|---|---|
| Schedule | 20% | Is the schedule maintained and is the job on time? |
| Financials | 20% | Is the job collecting cash, holding margin and coding its costs? |
| Safety | 20% | Are safety inspections happening and safety items closed? |
| Quality | 20% | Are quality inspections happening and quality items closed? |
| Project Controls | 20% | Are meetings held, submittals and RFIs current, daily logs written? |
| Risk | 0% | Subcontractor insurance on active work. Off until an executive turns it on |
Here are the measures under each pillar, with the reading each one takes and where it comes from.
| Pillar | Measure | Reading | Source |
|---|---|---|---|
| Financials | Cash Position | Cash collected ÷ cash paid out on the job | QuickBooks |
| Financials | Profitability (Gross) | Projected gross margin minus target margin, in points | Procore |
| Financials | Aging Balance | Balance-weighted average age of unpaid AR, in days | QuickBooks |
| Financials | Cost Coding | Share of job card spend coded to a Procore cost code within 7 days | The app's coding log |
| Schedule | 3-Week Look-Ahead | Days since the look-ahead was updated | Procore |
| Schedule | Monthly Schedule Update | Days since a new baseline schedule was saved | Procore |
| Schedule | Completion Variance | Days late ÷ baseline duration | Procore |
| Safety | Safety Inspections | Inspections closed or responded to this month | Procore |
| Safety | Safety Data | Overdue open safety observations and incidents | Procore |
| Quality | Quality Inspections | Inspections closed or responded to this month | Procore |
| Quality | Quality Data | Overdue open quality observations and punch items | Procore |
| Controls | OAC Meeting | Weeks missed in the rolling 4 weeks | Procore |
| Controls | Trade Partner Meeting | Weeks missed in the rolling 4 weeks | Procore |
| Controls | Submittals | Open submittals past due | Procore |
| Controls | RFIs | Open RFIs past their due date | Procore |
| Controls | Daily Logs | Weekdays this month without a daily log | Procore |
| Risk | Insurance | Subs on active work with expired or missing COIs | The app's compliance tracker |
Two measures (Safety forms and Punchlist) are shown as "Coming soon" and don't count yet. Risk ships at 0% and turns on from subcontractor compliance; that workflow is covered in subcontractor compliance tracking.
Notice how many of these are about inputs. That's on purpose. Ryan called Procore his "Trojan horse": the place everyone already works. A grade that rewards a current look-ahead, a written daily log and a coded card charge is how the inputs get standardized, and good inputs are what make the money numbers trustworthy. The same idea runs through our construction KPI scorecard starter set.
Bands and tolerances
Every measure turns its reading into a score from 0 to 1 using bands. A band has a From, a To, a score at each end, and a label. Inside a band the score is either flat or scales in a straight line between the two ends.
How a band turns a reading into a score
The default bands:
| Measure | Bands (reading → score) |
|---|---|
| Cash Position | 100% or more → 1.0 · 90-100% → 0.7 to 0.8 · under 90% → 0 |
| Profitability (Gross) | At or above target → 1.0 · up to 2.5 pts below → 0.75 · 2.5-5 below → 0.5 · 5-10 below → 0.25 · more than 10 below → 0 |
| Aging Balance | 1-30 days → 1.0 · 31-60 → 0.75 · 61-90 → 0.5 · over 90 → 0 |
| Cost Coding | 95% or more → 1.0 · 80-95% → 0.6 to 1.0 · under 80% → 0 |
| 3-Week Look-Ahead | Updated in last 7 days → 1.0 · otherwise 0 |
| Monthly Schedule Update | New baseline in last month → 1.0 · otherwise 0 |
| Completion Variance | On or ahead → 1.0 · late → 1 minus the variance (10% late scores 0.9) · late by the full duration → 0 |
| Inspections (safety, quality) | 10 or more → 1.0 · 5-9 → 0.8 to 1.0 · under 5 → 0 to 0.8 |
| Overdue items, submittals | 0 → 1.0 · 1-2 → 0.8 · 3-5 → 0.6 · 6-10 → 0.25 · more than 10 → 0 |
| RFIs past due | 0 → 1.0 · 1-3 → 0.8 · 4-5 → 0.6 · 6-10 → 0.25 · more than 10 → 0 |
| Meetings missed (rolling 4 weeks) | 0 → 1.0 · 1 → 0.75 · 2 or more → 0 |
| Daily Logs missed | 0 → 1.0 · 1-3 → 0.95 down to 0.8 · 4 or more → 0 |
Bands are half-open: a band includes its From and stops just short of its To, so a reading of exactly 80% falls in the 80-95% band, not the one below. The app refuses bands that overlap, and only the lowest and highest bands can be open-ended.
Some bands have cliffs on purpose. Cost Coding drops from 0.6 to 0 below 80%, because a job with more than a fifth of its card spend uncoded has a Procore job cost report nobody should trust. A gentle slope there would let a job hide a real problem behind good scores elsewhere.
Tolerances on the grade itself work the same way. The defaults:
| Threshold | Default | Meaning |
|---|---|---|
| On track from | 90 | Grade 90 and above is green |
| Monitor from | 75 | 75 to 89 is amber |
| (below Monitor) | Under 75 is red, Needs attention | |
| Minimum coverage | 50% | If less than half the weight has data, the job is Unscored, not graded |
| Below-target score | 80% | Any measure scoring under 0.8 is listed under "Below target" |
These are separate from the KPI tiles' own green, amber and red tolerances on the company dashboard. Grades judge a job; KPI tolerances judge a number. Both are set by executives.
The math, in four steps
From reading to grade
- Measure score. Look the reading up in its bands. 0 to 1.
- Pillar score. The average of the measures that have data and apply to the job's stage. Each measure can carry an in-pillar weight (default 1, so a plain average).
- Grade.
100 × Σ(pillar weight × pillar score) ÷ Σ(weights of pillars with data). - Band. Compare the grade with the thresholds above.
Two things fall out of step 3:
- Missing data doesn't lower the grade. A pillar with no data drops out and the others reweight. A job that just moved from precon has no safety inspections yet, and that shouldn't read as a safety problem.
- Weights don't have to add to 100%. Only the ratios matter, because the grade divides by the weight that has data. The screen offers Normalize to 100% to make them easier to read.
Measures also apply by stage. Pursuit and won jobs are in Precon, active jobs in Construction, closed jobs in Closeout. Inspections, safety and quality data and daily logs only count during construction.
Then two helpers:
- Weakest pillar is the pillar costing the most points:
weight × (1 − score). - Rank orders active and won jobs by grade, best first. Unscored jobs get no rank.
Worked example: 26-004 Clearfork Medical Office TI
This is a sample job in the proof of concept: a $1.28M medical office tenant improvement, about half built, with a margin that faded earlier in the year. Here's every reading and score.
| Pillar | Measure | Reading | Score |
|---|---|---|---|
| Schedule | 3-Week Look-Ahead | 6 days since update | 1.00 |
| Schedule | Monthly Schedule Update | 25 days since new baseline | 1.00 |
| Schedule | Completion Variance | 20% late | 0.80 |
| Schedule pillar | 0.933 | ||
| Financials | Cash Position | 0.92 | 0.72 |
| Financials | Profitability (Gross) | 7 pts below target | 0.25 |
| Financials | Aging Balance | 40 days | 0.75 |
| Financials | Cost Coding | 85% within 7 days | 0.733 |
| Financials pillar | 0.613 | ||
| Safety | Safety Inspections | 7 this month | 0.88 |
| Safety | Safety Data | 2 overdue | 0.80 |
| Safety pillar | 0.840 | ||
| Quality | Quality Inspections | 6 this month | 0.84 |
| Quality | Quality Data | 2 overdue | 0.80 |
| Quality pillar | 0.820 | ||
| Controls | OAC Meeting | missed 1 | 0.75 |
| Controls | Trade Partner Meeting | missed 1 | 0.75 |
| Controls | Submittals | 4 past due | 0.60 |
| Controls | RFIs | 2 past due | 0.80 |
| Controls | Daily Logs | 1 weekday missed | 0.95 |
| Controls pillar | 0.770 |
All five pillars have data, so coverage is 100% and the divisor is 1.0:
100 × 0.2 × (0.933 + 0.613 + 0.840 + 0.820 + 0.770) = 100 × 0.2 × 3.977 = 79.5
79.5 is between 75 and 90, so the band is Monitor. Financials costs 0.2 × (1 − 0.613) = 7.7 points, more than any other pillar, so it's the weakest. Seven measures score under 0.8 (Cash Position, Profitability, Aging Balance, Cost Coding, both meetings and Submittals), and they're listed under "Below target" with links to the source.
That gives the Monday question: profitability is 7 points under target and the cards aren't coded on time. Both are things a PM can act on this week.
For comparison, two other sample jobs:
| Job | Schedule | Financials | Safety | Quality | Controls | Grade | Band |
|---|---|---|---|---|---|---|---|
| 25-014 Panther Creek Retail Shell | 0.967 | 0.717 | 0.820 | 0.980 | 0.850 | 86.7 | Monitor |
| 26-004 Clearfork Medical Office TI | 0.933 | 0.613 | 0.840 | 0.820 | 0.770 | 79.5 | Monitor |
| 25-021 Trinity Bluff Mixed-Use Shell | 0.567 | 0.495 | 0.620 | 0.800 | 0.490 | 59.4 | Needs attention |
And one job that shows coverage at work: a won job that hasn't started has no Safety or Quality data, because those measures only apply during construction. Those pillars drop out, the remaining 60% of the weight has data, which is above the 50% minimum, and the job is graded on schedule, financials and controls alone.
Here's what that looks like on a project's Grade tab. The sample job in the screenshot is the top-ranked one at 96.
Grade, rank, coverage and points by pillar (sample data)
Every measure shows its reading, band and score (sample data)
Even on a 96, Cost Coding is the one amber bar: 88% of card spend coded within 7 days scores 81%. That's the approvals queue showing up in the grade.
Risk shows, but counts 0% until turned on (sample data)
Executive-adjustable weights, with a what-if
Executives and admins change the grade on Admin > Grade & weights. PMs see grades on their own jobs but can't change how they're calculated.
The page has three parts:
- Pillar weights. A slider or a typed percent for each pillar, with a stacked bar showing each one's share. Normalize to 100% rescales them.
- Measures. Expand a pillar to switch a measure on or off, change its in-pillar weight (0 to 10), or edit its bands. The page flags overlapping or broken bands before you can save.
- Thresholds. On track from, Monitor from, minimum coverage and the below-target score.
As you edit, a What-if ranking card switches from "Current" to "Preview (unsaved)" and shows every job's old and new grade, rank change and band, with chips like "1 changes band". The preview is calculated in memory. Nothing is saved and nothing is audited until you press Save. Saving writes each change to the audit log with the before and after, and every screen that uses the grade refreshes.
What-if: Financials at 40%
Here's a real what-if. Say the partners decide money matters most this quarter and set Financials to 40% and the other four pillars to 15% each.
| Job | Standard (20% each) | Financials 40%, others 15% | Band change |
|---|---|---|---|
| 25-014 Panther Creek Retail Shell | 86.7 | 82.9 | Monitor → Monitor |
| 26-004 Clearfork Medical Office TI | 79.5 | 74.98 | Monitor → Needs attention |
| 25-021 Trinity Bluff Mixed-Use Shell | 59.4 | 57.0 | Needs attention → Needs attention |
For 26-004: 100 × (0.15 × 0.933 + 0.40 × 0.613 + 0.15 × 0.840 + 0.15 × 0.820 + 0.15 × 0.770) = 74.98. It lands a hair under 75 and turns red. The order of the jobs doesn't change, but one job now shows up in the partners' Needs attention list.
That's what the preview is for. Before saving, ask whether the new weights describe the business you want, or just produce the ranking you expected. If a weight change moves one job across a line by 0.02 points, the thresholds might be the thing to look at, not the weights.
Our advice on tuning:
- Run the defaults for 4 to 6 weeks first. You need a few weeks of readings before you know which measures are noisy.
- Change one thing at a time, and write down why in the audit note or the partners' meeting notes.
- Don't tune a measure to make a favorite job green. Check the readings against Procore and QuickBooks first. Often the "bad" score is a data entry gap, which is exactly what the grade should catch.
- Review quarterly, and whenever you turn on a new pillar such as Risk.
- Reset to standard is always there if a round of edits goes sideways. It restores the default weights, bands and thresholds, and logs the old ones.
Where the grade shows up
The grade isn't only on the project page. It feeds:
- The Projects list, as a column next to contract, % complete and margin.
- Project ranking & grades on the company dashboard: portfolio average (83 on the sample data, across 6 graded jobs: 2 on track, 3 monitor, 1 needs attention).
- KPI tiles for Average project grade and Projects on track %.
- Alerts when a grade drops or a weakest pillar changes.
- The weekly digest email.
- The AI assistant and the read-only API, so an agent asked "which jobs need attention?" gives the same answer as the dashboard. That's covered in giving an AI vendor read-only API and MCP access.
Download the template
The project grade scorecard template (CSV) has one row per measure: pillar, default weight, measure, reading definition, unit, source, every band, and readings and scores for three sample jobs, followed by pillar scores, grades and bands. Use it to try your own weights in a spreadsheet before you build anything, or hand it to whoever runs your reporting.
Where this fits
The grade is one screen in the project operating system tour. Its Financials pillar leans on two other pieces: the approvals queue, which drives Cost Coding, and the month-end cost-to-complete review, which sets the projected margin that Profitability compares with target. For the wider KPI set and how to validate each number against its source, see the KPI scorecard starter set and construction data quality rules.
Want a grade for your jobs?
If you can feel which jobs are in trouble but can't show it on one page, we can build a grade from the data you already have in Procore and QuickBooks, with weights your partners control. Email charley@buildflows.ai or tell us about your jobs.
Frequently asked questions
How do you calculate a construction project grade?
Score each measure from 0 to 1 by looking its reading up in bands, average the measures in each pillar, then compute 100 times the sum of each pillar's weight times its score, divided by the total weight of pillars that have data. Compare the result with thresholds such as 90 for on track and 75 for monitor.
What pillars should a construction project scorecard include?
A practical default is schedule, financials, safety, quality and project controls at 20% each. Financials covers cash collected versus paid, margin versus target, AR age and cost coding. Controls covers meetings, submittals, RFIs and daily logs. A risk pillar for subcontractor insurance can be added once compliance data is tracked.
What happens when a project has no data for a pillar?
That pillar drops out and the remaining pillars are reweighted, so the grade isn't penalized for data that can't exist yet, such as safety inspections before construction starts. If less than half of the total weight has data, the project is shown as unscored instead of graded.
Who should be able to change the grade weights?
Executives and admins. Project managers should see their jobs' grades but not change the method. Every saved change should be audited with before and after values, and a what-if preview should show which projects change rank or band before saving.
Should a project grade be used to evaluate project managers?
Use it to ask better questions, such as why a job's financials pillar is low, rather than as a performance review. A grade used to punish people tends to get gamed. Check low scores against the source data first, since many come from data entry gaps.
How often should scorecard weights and tolerances be tuned?
Run the defaults for four to six weeks to see which measures are noisy, then change one thing at a time and record why. Review quarterly and whenever a new pillar, such as risk, is turned on.
Next step
Trying to automate a report like this?
Discuss your current reporting process: what the team does today, which systems are involved, and what you want to change.
Prefer email? charley@buildflows.ai
Keep learning
Reporting & analytics · November 18, 2026
What Good Looks Like: A Starter KPI Scorecard for a Small GC
A starter KPI scorecard for a small GC, built from a discovery call with Cattlemen Construction Services: 12 KPIs in four groups (Money, Delivery, Field discipline, Admin), each with a definition, source system, formula, default green/amber/red tolerance and reason. Covers standardizing Procore inputs first, scoring weekly, validating each number against its source of truth, role-based views, tuning tolerances after 4-6 weeks and using red tiles to ask what happened rather than to punish.
Custom applications · November 19, 2026
A Contractor's Project Operating System, Screen by Screen: What Each Role Sees and Why
A screen-by-screen tour of the Cattlemen OS proof of concept built for Cattlemen Construction Services in Fort Worth, Texas, on sample data over QuickBooks Online, Procore, Ramp and Microsoft 365. Covers sign-in and Home, My expenses and the approvals queue that gets card spend onto Procore cost codes, the Projects list with convert to won and SharePoint folders, the project page tabs (overview, grade, job cost, expenses, subs, files), the weighted project grade, the month-end cost-to-complete close, the company dashboard, alerts, reports, the platform console with read-only view as, the help center and the AI brain connection through iframe, read-only API and MCP. For each screen: what it shows, which role sees it and why, with sample numbers and timestamps from the walkthrough video.
Reporting & analytics · November 19, 2026
Month-End Cost-to-Complete Review: PM Forecast, Executive Sign-Off and a Locked WIP
The month-end close in the Cattlemen OS proof of concept for Cattlemen Construction Services, on sample data. Defines cost to date, cost to complete, estimate at completion, cost-to-cost percent complete, earned revenue, over and under billing, projected margin and margin fade, and works every formula on sample job 26-004 (EAC $1,100,075 on a $1,278,000 contract, 13.9% margin, $69,823 under billed). Walks through opening the month, the PM's cost-code forecast with prefill rules, submit, executive review with fade flags (margin down more than 1 point or EAC up more than 2%) and questions to ask, approve or send back, lock and sign off, the close pack, and admin unlock with a reason. Includes a six-job portfolio table and a CSV review worksheet.