Build Flows

Integration guide

Procore and Microsoft SharePoint & OneDrive integration

The pattern we recommend keeps bids in SharePoint and real work in Procore. A Create new project action numbers the job and builds its folder set at RFP; Convert to won creates the Procore project with the same number and writes its ID back. Lost bids never reach Procore, so project lists and reports hold only real work.

System facts last verified October 2026 against the vendors' documentation (sources below). Confirm details with Procore Technologies and Microsoft before you build.

Procore and SharePoint side by side

API style
ProcoreREST/JSON. Procore states that direct database access and RDBMS, XML or SOAP integrations aren't supported.
SharePointREST/JSON through Microsoft Graph (graph.microsoft.com/v1.0), with SDKs for common languages. Microsoft recommends Graph over SharePoint's CSOM and REST APIs, which usually cost more against throttling limits.
Authentication
ProcoreOAuth 2.0, registered as an app in the Procore Developer Portal: authorization code (acts as a specific user) or client credentials through a Developer Managed Service Account (DMSA) with company and project permissions. Traditional service accounts were sunset on March 18, 2025.
SharePointMicrosoft Entra ID OAuth 2.0 app registration. Delegated permissions act as the signed-in user and never exceed that user's access; application permissions such as Sites.Read.All or Files.ReadWrite.All need admin consent. Sites.Selected and the newer Selected scopes limit an app to specific sites, lists or files, each granted explicitly.
Webhooks / events
ProcoreYes. Company- or project-level create, update and delete triggers; Procore recommends payload v4.0 for new integrations. Delivery is best-effort with retries, and events are discarded after 12 hours of continuous failure, so pair webhooks with a periodic reconciliation sync.
SharePointYes. Graph change notifications for a SharePoint list or a drive's root folder hierarchy; subscriptions last under 30 days and must be renewed, and Microsoft lists up to 6 hours' maximum latency. A notification says something changed; a delta query with a saved token fetches what changed.
Rate limits
ProcoreAn hourly (60-minute) limit and a 10-second spike limit, reported in X-Rate-Limit-Limit, -Remaining and -Reset headers; exceeding either returns 429, and 503 with Retry-After signals platform load. Procore publishes no fixed default: its rate-limiting page uses sample headers (600 per hour, 25 per spike window), warns not to assume a fixed window such as 3,600/hour, says values can change, and lets apps request an increase. Every request counts, including failed ones.
SharePointResource units per app per tenant, scaled by license count: up to 1,000 licenses, 1,250 per minute and 1,200,000 per 24 hours. A single-item read or delta with a token costs 1 unit, a list or write 2, a permissions call 5. Throttled calls return 429 or 503 with Retry-After, and still count against the limit.
Sandbox
ProcoreYes. A developer sandbox with seed data is created when you register an app (you can have many). Customers can also enable on-demand and monthly sandboxes; the monthly one is refreshed from production each month. Not available to Federal Zone customers.
SharePointThe Microsoft 365 Developer Program's E5 sandbox (25 licenses, short-lived by design) is eligibility-based, for example through a Visual Studio Professional or Enterprise subscription or qualifying partner programs. Many teams test against a dedicated site in their own tenant.
Exports and files
ProcoreNo bulk export API confirmed; reporting integrations page through list endpoints. Procore Analytics is a separate product.
SharePointFiles download through driveItem content; list data reads through list items with expanded fields. Delta queries return changes since a saved token and are the cheapest way to sync.
Marketplace / partners
ProcoreProcore App Marketplace and the Procore Technology Partner Program (application, technical review, certification, agreement, listing).
SharePointMicrosoft AppSource and the Microsoft AI Cloud Partner Program. Not needed for a single-tenant integration.

Who owns what

  • One direction at project start: a won project in the register creates the project-management project with the same number, and its ID is written back.
  • Once the job is live, RFIs, submittals and drawings are worked in project management; exports land in the project folder at closeout.

What syncs between Procore and SharePoint

The typical shape for this pair. Every row is typical: confirm it against your configuration in discovery.

ProcoreSharePointProject register → Procore projectProject number and nameProcore project ID and linkFolder set and Client columnRFIs, submittals, drawings and punch itemsContracts, insurance and pay app backupCloseout documents
Arrows point from the system that sends to the system that receives. Dashed means it stays put.
ObjectDirectionSystem of record
Project register → Procore projectSharePoint to ProcoreSharePoint Projects list until won; Procore after
Typical frequency: On Convert to won. Notes: Pressing Convert to won sets Status = Won and creates the Procore project through its REST API with the same number and name, plus fields you choose such as address or template.(Typical: confirm against your configuration.)
Project number and nameSharePoint to ProcoreSharePoint Projects list
Typical frequency: At RFP. Notes: Assign a YY-NNN number when the RFP arrives and never reuse it. The folder, the list row and Procore must match exactly.(Typical: confirm against your configuration.)
Procore project ID and linkProcore to SharePointProcore, written once
Typical frequency: On project creation. Notes: Save the Procore project ID and link on the list row, so the register, the folder and reporting join on IDs, not names.(Typical: confirm against your configuration.)
Folder set and Client columnnot syncedSharePoint
Typical frequency: At RFP (Create new project). Notes: Create new project adds the list row, copies the folder template, sets folder default values for Client and Project Number, and writes the folder link back. Procore isn't involved.(Typical: confirm against your configuration.)
RFIs, submittals, drawings and punch itemsnot syncedProcore
Typical frequency: Worked in Procore. Notes: Once a job is live these are worked in Procore. Don't mirror them into SharePoint folders.(Typical: confirm against your configuration.)
Contracts, insurance and pay app backupnot syncedSharePoint
Typical frequency: As filed. Notes: Material Procore doesn't hold well stays in the project folder; client-level material stays in the Clients library.(Typical: confirm against your configuration.)
Closeout documentsProcore to SharePointProcore until closeout
Typical frequency: At closeout. Notes: Export closeout documents from Procore into the project's Closeout folder, then archive the folder on schedule.(Typical: confirm against your configuration.)

Directions, owners and frequencies are the typical pattern from our integration guides and mapping workbook. Confirm each one against your configuration in discovery.

Is a native connector enough?

We haven't confirmed a documented native connector for this pattern. Check the Procore App Marketplace for a document connector first, but the two automations are small: Power Automate or Microsoft Graph code for the folders and list, and Procore's REST API for the project. Build when you want the numbering, folder template and Procore creation governed in one place.

Compare native connectors with a custom build

Common gotchas

  • Check for an existing Procore project with the same number before creating one, so a retried Convert to won can't create duplicates.
  • Keep Procore credentials out of the flow itself: Power Automate's HTTP action needs a premium license, and a small service holding the credentials in a key vault is easier to govern.
  • Grant the automation's app only the operations site through Sites.Selected; Sites.Read.All or Files.ReadWrite.All would reach every site and OneDrive in the tenant.
  • SharePoint paths are limited to 400 characters decoded, and deep client and project trees hit it first on synced laptops. Keep project folders one level under the library and the template two levels deep.
  • Views are convenience, not security. Separate a client's work with its own library and permissions rather than unique permissions on hundreds of folders.

Sources

Frequently asked questions

Can SharePoint create a Procore project?

Yes, through an automation: a list row marked won triggers a flow or small service that creates the project with Procore's REST API, using the same number and name, and writes the Procore project ID back to the row.

Should project documents live in SharePoint or Procore?

Both, with a rule. Bids, contracts, insurance and pay app backup live in SharePoint; RFIs, submittals, drawings and punch items are worked in Procore once the job is live, and closeout exports are filed back to SharePoint.

Why keep lost bids out of Procore?

So Procore's project list, reports and any dashboard built on them contain only real work. Bids get a number and folder in SharePoint at RFP and reach Procore only when they're won.

Next step

Connecting Procore and SharePoint?

Bring one real job and the records you want to move. We'll walk through what syncs, who owns each record, and what to check first.