Are we billed ahead of or behind the work on each job?
% complete = cost to date ÷ EAC. Earned = % complete × revised contract. Billed − earned: positive is over billing (a liability), negative is under billing (an asset).
Red flag: overbilled by more than 10% of contract, or a big underbilling with no pay app due.
2Cash + 13-week forecast
QBOProcore
Will cash hold up for the next 13 weeks?
Start at today's bank balance. In: open AR on due date + each client's average days late, plus scheduled billings. Out: AP by due date, payroll and overhead run rate, committed sub payments.
Red flag: the projected low point dips under the floor you set (for example two payrolls).
Where is each job against budget, by cost code?
Budget and committed from Procore, actual in QuickBooks, actual visible in Procore, variance, % used. Uncoded card spend gets its own line.
Red flag: QuickBooks actual above Procore actual on a code. That's spend the PM can't see.
4Profitability + portfolio
ProcoreQBO
Which jobs, clients and PMs make money, and which don't?
Margin = (contract − EAC) ÷ contract. Fade = points lost vs the bid. Gross profit to date = earned − cost. Months of backlog = backlog ÷ average monthly revenue.
Red flag: margin fade that keeps sliding week to week; under ~3 months of backlog.
5Commitments + buyout
Procore
Is every budget line bought out, and is anything over-committed?
By cost code: budget, committed, uncommitted. Buyout variance = budget − committed on bought-out codes (+ savings, − overrun). Commitment log with billed, retainage, remaining.
Red flag: a negative buyout on a code, or uncommitted budget on a job past 50% complete.
6Vendor spend + uncoded aging
RampProcoreQBO
Who do we pay, how much, and what is still uncoded?
Card spend, commitment billings, AP open and retainage payable. Top vendors, spend by GL and cost code, and card spend not yet on a cost code, aged by days.
Red flag: dollars in the 30+ day uncoded bucket. Procore can't see that cost.
7Card spend coding
RampApp
Who still has card charges to code, and how fast do they reach Procore?
By cardholder and GL category: to code, coded, approved, synced, median days to code. Unreconciled spend by project.
Red flag: charges uncoded after 7 days; the same names at the top every week.
What needs a person today?
QuickBooks ≠ Procore gaps, uncoded > 7 days, sync errors, negative-margin jobs, overbilled > 10%. Each row links to where it gets fixed.
Red flag: any red item, and anything still open from last week.